[EventId:202410291710_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 17:10
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1710 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - AEMO Intervention Event - SA region 25/10/2024
Cancellation - AEMO Intervention Event - SA region 25/10/2024
Refer to Market Notice 119414
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 29/10/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119604
Direction is cancelled from: 1700 hrs 29/10/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119573
Direction is cancelled from: 1700 hrs 29/10/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119651
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 29/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0730 hrs 30/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1730 hrs 30/10/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119651
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 29/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0030 hrs 30/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 31/10/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
[EventId:202410291510_confirmed] Prices for interval 29-Oct-2024 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 October 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Oct-2024 15:10.
In accordance with Market Notice 119647 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410291530_confirmed] Prices for interval 29-Oct-2024 15:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 October 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Oct-2024 15:30.
In accordance with Market Notice 119652 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202410291525_confirmed] Prices for interval 29-Oct-2024 15:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 October 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Oct-2024 15:25.
In accordance with Market Notice 119650 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.