Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2300 hrs.
The Actual LOR1 condition is forecast to exist until 0200 hrs
The capacity reserve requirement is 600 MW
The minimum capacity reserve available is 520 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
[1.] From 0000 hrs 25/09/2024 to 0100 hrs 25/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 580 MW.
[2.] From 0700 hrs 25/09/2024 to 0730 hrs 25/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 547 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118429 is cancelled at 2000 hrs 24/09/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 24/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118428 is cancelled at 1745 hrs 24/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
From 0000 hrs 25/09/2024 to 0100 hrs 25/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 571 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 24/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
[1.] From 1900 hrs 24/09/2024 to 1930 hrs 24/09/2024.
The forecast capacity reserve requirement is 593 MW.
The minimum capacity reserve available is 584 MW.
[2.] From 2330 hrs 24/09/2024 to 0000 hrs 25/09/2024.
The forecast capacity reserve requirement is 589 MW.
The minimum capacity reserve available is 583 MW.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 24/09/2024
Network Augmentation Commissioned - NSW Region - 24/09/2024
At 1535 hrs Buronga - Redcliffs X1 220 kV line has been commissioned.
Manager NEM Real Time Operations
Direction - SA region 24/09/2024
Direction - SA region 24/09/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 24/09/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - SA region 24/09/2024
Direction - SA region 24/09/2024
Refer to Market Notice 118426
In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 24/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1000 hrs 25/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 26/09/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations