Market Notices

118388RESERVE NOTICE23/09/2024 05:54:01 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118387 is cancelled at 05:40 hrs 23/09/2024.

Manager NEM Real Time Operations
     
118387RESERVE NOTICE23/09/2024 05:16:09 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 279 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
118384RESERVE NOTICE22/09/2024 10:45:15 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118382 is cancelled at 22:40 hrs 22/09/2024.

Manager NEM Real Time Operations
     
118382RESERVE NOTICE22/09/2024 10:30:45 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 23/09/2024 to 2000 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 322 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
118379MARKET INTERVENTION23/09/2024 03:59:18 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 118386

Direction is cancelled from: 0400 hrs 23/09/2024

Manager NEM Real Time Operations
     
118378MARKET INTERVENTION23/09/2024 04:00:34 AM

Cancellation - AEMO Intervention Event - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/09/2024

Refer to Market Notice 118376

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 23/09/2024.



Manager NEM Real Time Operations
     
118376MARKET INTERVENTION22/09/2024 07:06:53 PM

Direction - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1855 hrs on 22/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118375MARKET INTERVENTION22/09/2024 06:50:12 PM

Direction - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/09/2024



In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1850 hrs 22/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1850 hrs 22/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1950 hrs 22/09/2024.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118374RESERVE NOTICE22/09/2024 04:20:38 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118364 has been updated at 1600 hrs to the following:

[1.] From 1830 hrs 23/09/2024 to 2100 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 481 MW.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm