118364RESERVE NOTICE22/09/2024 12:55:43 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

[1.] From 1800 hrs 23/09/2024 to 1830 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 432 MW.

[2.] From 2030 hrs 23/09/2024 to 2130 hrs 23/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 448 MW.

Manager NEM Real Time Operations
     
118363RESERVE NOTICE22/09/2024 12:54:20 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1830 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 260 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
118362RESERVE NOTICE22/09/2024 03:02:38 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118361 is cancelled at 0300 hrs 22/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
118361RESERVE NOTICE21/09/2024 10:35:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1430 hrs 24/09/2024 to 1600 hrs 24/09/2024.
The forecast capacity reserve requirement is 516 MW.
The minimum capacity reserve available is 462 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
118360NON-CONFORMANCE21/09/2024 07:20:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 21/09/2024 15:00 to 21/09/2024 19:20
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118359RESERVE NOTICE21/09/2024 03:02:14 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118358 is cancelled at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     
118358RESERVE NOTICE21/09/2024 12:56:24 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 22/09/2024 to 2030 hrs 22/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.

Manager NEM Real Time Operations
     
118357MARKET INTERVENTION21/09/2024 03:03:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118339

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 22/09/2024.

The direction update is issued at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     
118356MARKET INTERVENTION21/09/2024 03:00:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118340

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 22/09/2024.

The direction update is issued at 1500 hrs 21/09/2024.

Manager NEM Real Time Operations
     