Market Notices

115061SETTLEMENTS RESIDUE23/02/2024 07:35:22 PM

[EventId:202402231935_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 23 February 2024 19:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1935 hrs on 23 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 23 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1935 hrs on 23 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115060SETTLEMENTS RESIDUE23/02/2024 07:30:17 PM

[EventId:202402231930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 February 2024 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 February 2024.

Refer to market notice: 115058

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 23 February 2024.

This is an AEMO autogenerated Market Notice.
115059SETTLEMENTS RESIDUE23/02/2024 07:20:18 PM

[EventId:202402231920_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 23 February 2024 19:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 23 February 2024.

Refer to market notice: 115050

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1920 hrs on 23 February 2024.

This is an AEMO autogenerated Market Notice.
115058SETTLEMENTS RESIDUE23/02/2024 07:05:50 PM

[EventId:202402231905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 February 2024 19:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 23 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1905 hrs on 23 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115057RECLASSIFY CONTINGENCY23/02/2024 07:04:25 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 23/02/2024 19:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 115041

Auto-generated on behalf of Manager NEM Real Time Operations
115056SETTLEMENTS RESIDUE23/02/2024 07:00:21 PM

[EventId:202402231900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 February 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 February 2024.

Refer to market notice: 115046

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 23 February 2024.

This is an AEMO autogenerated Market Notice.
115055RESERVE NOTICE23/02/2024 06:50:07 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115025 is cancelled at 1845 hrs 23/02/2024.

Manager NEM Real Time Operations
115054SETTLEMENTS RESIDUE23/02/2024 06:30:23 PM

[EventId:202402231830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 23 February 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 23 February 2024.

Refer to market notice: 115049

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 23 February 2024.

This is an AEMO autogenerated Market Notice.
115053SETTLEMENTS RESIDUE23/02/2024 06:15:22 PM

[EventId:202402231815_NRM_NSW1_QLD1_stopped] NEGRES CONSTRAINT NRM_NSW1_QLD1 ceased operating from 23 February 2024 18:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 23 February 2024.

Refer to market notice: 115052

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to QLD directional interconnector.

The negative residue constraint NRM_NSW1_QLD1 ceased operating at 1815 hrs on 23 February 2024.

This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm