Market Notices

115030PRICES UNCHANGED23/02/2024 01:31:38 PM

[EventId:202402231305_confirmed] Prices for interval 23-Feb-2024 13:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 23 February 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Feb-2024 13:05.

In accordance with Market Notice 115021 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
115029SETTLEMENTS RESIDUE23/02/2024 01:26:42 PM

[EventId:202402231325_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 February 2024 13:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 23 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1325 hrs on 23 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115028PRICES SUBJECT TO REVIEW23/02/2024 01:25:14 PM

[EventId:202402231330_review] Prices for interval 23-Feb-2024 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 23 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115027PRICES SUBJECT TO REVIEW23/02/2024 01:20:19 PM

[EventId:202402231325_review] Prices for interval 23-Feb-2024 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 23 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115026PRICES SUBJECT TO REVIEW23/02/2024 01:15:23 PM

[EventId:202402231320_review] Prices for interval 23-Feb-2024 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 23 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115025RESERVE NOTICE23/02/2024 01:21:26 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115016 has been updated at 1315 hrs to the following:

[1.] From 1730 hrs 23/02/2024 to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1097 MW.

Manager NEM Real Time Operations
115024PRICES SUBJECT TO REVIEW23/02/2024 01:10:16 PM

[EventId:202402231315_review] Prices for interval 23-Feb-2024 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 23 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115023PRICES SUBJECT TO REVIEW23/02/2024 01:05:19 PM

[EventId:202402231310_review] Prices for interval 23-Feb-2024 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 23 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
115022SETTLEMENTS RESIDUE23/02/2024 01:01:23 PM

[EventId:202402231300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 23 February 2024 13:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 23 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 February 2024.

Refer to market notice: 115019

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 23 February 2024.