86873GENERAL NOTICE10/06/2021 07:56:21 AM

Planned outage of Heywood to Mortlake 500kV line Circuit Breaker (213) in the Victoria region on 18/06/2021

AEMO ELECTRICITY MARKET NOTICE

The Heywood Mortlake power station No. 2 line No. 2 bus 500kV Circuit Breaker (213) in the Victoria (VIC) region is planned to be out of service from 0700 hrs to 1900 hrs on 18/06/2021.

A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM. If separation occurs, load may be interrupted due to the operation of the Automatic Under Frequency Load Shedding (AUFLS) scheme in SA.

The credible separation contingency is managed as follows:

-When power transfer is from SA to Victoria, contingency lower FCAS will be sourced from SA.
-When power transfer is from Victoria to SA, due to the 47-52Hz island separation frequency band advised by the SA jurisdiction, contingency raise FCAS is not sourced in SA and the AUFLS scheme may respond to low frequency events.
-Power transfer will be restricted on Victoria - South Australia interconnector (Heywood interconnector) to manage system security following the loss of the next contingency.

Forecast capacity reserves in the SA region are currently sufficient to meet electricity demand during the planned outage.

The following constraint sets have been invoked for this outage:

F-I-HYSE
I-VS_050
S-X_BC_CP
V-HYCB_210_213

Refer AEMO Network Outage Schedule (NOS) for further details.

Diyoni Hoole
AEMO Operations
86872PRICES SUBJECT TO REVIEW10/06/2021 07:50:18 AM

[EventId:202106100755_review] Prices for interval 10-Jun-2021 07:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0750 hrs on 10 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 10-Jun-2021 07:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
86871PRICES SUBJECT TO REVIEW10/06/2021 07:47:13 AM

[EventId:202106100750_review] Prices for interval 10-Jun-2021 07:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0745 hrs on 10 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 10-Jun-2021 07:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
86870PRICES UNCHANGED10/06/2021 07:45:19 AM

[EventId:202106100730_confirmed] Prices for interval 10-Jun-2021 07:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0745 hrs on 10 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 10-Jun-2021 07:30.

In accordance with Market Notice 86864 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86869PRICES UNCHANGED10/06/2021 07:48:02 AM

[EventId:202106100725_confirmed] Prices for interval 10-Jun-2021 07:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0745 hrs on 10 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 10-Jun-2021 07:25.

In accordance with Market Notice 86863 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86868PRICES UNCHANGED10/06/2021 07:46:28 AM

[EventId:202106100720_confirmed] Prices for interval 10-Jun-2021 07:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0745 hrs on 10 June 2021

PRICES ARE NOW CONFIRMED for dispatch interval 10-Jun-2021 07:20.

In accordance with Market Notice 86862 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
86867PRICES SUBJECT TO REVIEW10/06/2021 07:40:18 AM

[EventId:202106100745_review] Prices for interval 10-Jun-2021 07:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0740 hrs on 10 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 10-Jun-2021 07:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
86866PRICES SUBJECT TO REVIEW10/06/2021 07:35:15 AM

[EventId:202106100740_review] Prices for interval 10-Jun-2021 07:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0735 hrs on 10 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 10-Jun-2021 07:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
86865PRICES SUBJECT TO REVIEW10/06/2021 07:30:11 AM

[EventId:202106100735_review] Prices for interval 10-Jun-2021 07:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0730 hrs on 10 June 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 10-Jun-2021 07:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs