113667MARKET SYSTEMS23/01/2024 02:28:57 PM

CHG0082564:EMMS - WebPortal

Change Number: CHG0082564
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - WebPortal
Change Title: Identity Service Site Transfer
Change Start Date & Time: 30/01/2024 11:00:00 AEST
Change End Date & Time: 30/01/2024 19:00:00 AEST
Outage Start Date & Time: 30/01/2024 13:10:00 AEST
Outage End Date & Time: 30/01/2024 13:30:00 AEST
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Markets Portal
Identity Service might have an intermittemt outage of maximum 5 minutes during the outage period impacting user login.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities
113637SETTLEMENTS RESIDUE22/01/2024 07:25:24 PM

[EventId:202401221925_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2024 19:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1925 hrs on 22 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.

Refer to market notice: 113632

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1925 hrs on 22 January 2024.

This is an AEMO autogenerated Market Notice.
113632SETTLEMENTS RESIDUE22/01/2024 06:25:20 PM

[EventId:202401221825_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2024 18:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 22 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1825 hrs on 22 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113606MARKET SYSTEMS22/01/2024 02:38:48 PM

CHG0082504:MSATS - Business to Business data exchange

Change Number: CHG0082504
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113605SETTLEMENTS RESIDUE22/01/2024 02:31:02 PM

[EventId:202401221430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2024 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 22 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.

Refer to market notice: 113600

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 22 January 2024.

This is an AEMO autogenerated Market Notice.
113600SETTLEMENTS RESIDUE22/01/2024 11:00:21 AM

[EventId:202401221100_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2024 11:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 22 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1100 hrs on 22 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113595NON-CONFORMANCE22/01/2024 05:10:18 AM

NON-CONFORMANCE Region VIC1 Monday, 22 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 22 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 22/01/2024 04:15 to 22/01/2024 05:10
Amount: 27 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
113586SETTLEMENTS RESIDUE21/01/2024 09:30:17 PM

[EventId:202401212130_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 21 January 2024 21:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2130 hrs on 21 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 January 2024.

Refer to market notice: 113580

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2130 hrs on 21 January 2024.

This is an AEMO autogenerated Market Notice.
113580SETTLEMENTS RESIDUE21/01/2024 08:35:26 PM

[EventId:202401212035_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 21 January 2024 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 21 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 2035 hrs on 21 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm