Update - Raise Regulation FCAS Increased - 24/06/16
Update to MArket Notice 53974
Variation to FCAS regulation requirements: NEM Global - 24/06/16.
Constraint Set F-MAIN_RREG_0350 was revoked at 1700 hrs..
Manager NEM Real Time Operations
Raise Regulation FCAS Increased - 24/06/16
Variation to FCAS regulation requirements: NEM Global - 24/06/16.
FCAS Raise regulation requirements have been increased to manage time error to within standards.
The following constraints have been invoked to manage raise regulation requirements.
F-MAIN_RREG_0350 invoked from 1555 hrs until further notice.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Refer AEMO Electricity Market Notice 54126
There is no longer any lightning activity in the vicinity of the Rowville - Yallourn No.5 & No.6 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1500 hrs.
Constraint Set
V-ROYP56_R_N-2 revoked.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Lightning is occurring near the Rowville - Yallourn No.5 & No.6 220 kV Lines.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1425 hrs 24/06/16 until further notice.
Constraint Set
V-ROYP56_R_N-2 invoked.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 24 June 2016
NON-CONFORMANCE SA1 Region Friday, 24 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: TORRA2
Duration: 24/06/2016 12:15 to 24/06/2016 12:20
Amount: -25 MW
Constraint: NC-S_TORRA2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - APD to Heywood No.1 500kV line (Vic Region) - 24/06/16.
Inter-Regional Transfer limit variation - APD to Heywood No.1 500kV line (Vic Region) 24/06/16.
There is a short notice outage of APD - Heywood No.1 500kV line.
The following Constraint Set was invoked from 1050 hrs.
V-APHY1_2
This Constraint Set contain equations with the following interconnectors on the LHS
V-SA
Refer to AEMO Network Outage Schedule for further details.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Eildon - Mt. Beauty No. 1 and No. 2 220 kV Lines in Victoria due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Eildon - Mt. Beauty No. 1 and No. 2 220 kV Lines in Victoria due to Lightning.
Refer AEMO Electricity Market Notice 54120
There is no longer any lightning activity in the vicinity of the Eildon - Mt. Beauty No. 1 and No. 2 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0030 hrs.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 and No.3 220 kV Lines in Victoria due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 and No.3 220 kV Lines in Victoria due to Lightning.
Refer AEMO Electricity Market Notice 54119
There is no longer any lightning activity in the vicinity of the Dederang - Glenrowan No.1 and No.3 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0030 hrs.
Constraint Set V-DDGN_N-2 revoked.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 24 June 2016
NON-CONFORMANCE SA1 Region Friday, 24 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: OSB-AG
Duration: 24/06/2016 00:00 to 24/06/2016 00:05
Amount: -32 MW
Constraint: NC-S_OSB-AG