Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 31/05/2024 00:24 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 31/05/2024 00:24 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1830 hrs 03/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1751 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116724 is cancelled at 1400 hrs 21/05/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116723 is cancelled at 1400 hrs 21/05/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116722 for the 21/05/2024 is cancelled at 1600 hrs 20/05/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.116700 has been updated at 1450 hrs to the following:
[1.] From 1630 hrs 20/05/2024 to 1900 hrs 20/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 958 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0000 hrs to 0130 hrs 23/05/2024.
The forecast capacity reserve requirement is 1640 MW.
The minimum capacity reserve available is 1422 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116703 has been updated at 1400 hrs 20/05/2024 to the following:
1. From 0600 hrs to 0800 hrs 22/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 1386 MW.
2. From 1630 hrs to 2359 hrs 22/05/2024.
The forecast capacity reserve requirement is 1610 MW.
The minimum capacity reserve available is 1337 MW.
AEMO Operations