Market Notices

116940NON-CONFORMANCE11/06/2024 02:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116939RECLASSIFY CONTINGENCY11/06/2024 02:19:06 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 11/06/2024 14:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 116937

Auto-generated on behalf of Manager NEM Real Time Operations
     
116937RECLASSIFY CONTINGENCY11/06/2024 01:17:02 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 11/06/2024 13:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
116933RESERVE NOTICE11/06/2024 01:09:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 0830 hrs 12/06/2024 to 0900 hrs 12/06/2024.
The forecast capacity reserve requirement is 421 MW.
The minimum capacity reserve available is 393 MW.

[2.] From 0930 hrs 12/06/2024 to 1000 hrs 12/06/2024.
The forecast capacity reserve requirement is 419 MW.
The minimum capacity reserve available is 407 MW.

Manager NEM Real Time Operations
     
116932NON-CONFORMANCE11/06/2024 12:05:16 PM

NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116930MARKET SYSTEMS11/06/2024 08:18:14 AM

CHG0089972 | Completed | Production | Planned Maintenance to Norwest Internet firewall.

Change Number: CHG0089972
Notification issued to: Market Notice Notification
Type: Completed
Change Type: Normal Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
116927NON-CONFORMANCE10/06/2024 11:40:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/06/2024 23:35 to 10/06/2024 23:40
Amount: 34 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116926RESERVE NOTICE10/06/2024 05:51:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 17/06/2024 to 2100 hrs 17/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1530 MW.

Manager NEM Real Time Operations
     
116922NON-CONFORMANCE10/06/2024 08:30:13 AM

NON-CONFORMANCE Region SA1 Monday, 10 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 10 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CATHROCK
Duration: 10/06/2024 08:10 to 10/06/2024 08:30
Amount: 22 MW
Constraint: NC-S_CATHROCK

Auto-generated on behalf of Manager NEM Real Time Operations
     