115663INTER-REGIONAL TRANSFER16/03/2024 05:12:33 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 16/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 16/03/2024

A planned outage of Red Cliffs - Buronga 0X1 220 kV Line in the Vic region was scheduled from 0500 hrs 16/03/2024 to 1900 hrs 16/03/2024.

The outage has been completed and returned to service at 1655 hrs 16/03/2024.

Constraint set(s) revoked:
I-BURC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
115652INTER-REGIONAL TRANSFER15/03/2024 02:52:51 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 1445 hrs 15/03/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
115627INTER-REGIONAL TRANSFER15/03/2024 06:31:39 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

At 0600 hrs 15/03/2024 there was a short notice outage of Robertstown - Tungkillo No. 2 275 kV Line.
At 0615 hrs 15/03/2024 there was a short notice outage of Tungkillo - Para No. 1 275 kV Line.

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505DC4C from 06:00 hrs until further notice

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
115626INTER-REGIONAL TRANSFER15/03/2024 05:10:47 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505D0BC from 04:40 hrs to 05:10 hrs
CA_SYDS_5505D516 from 04:55 hrs to 05:10 hrs

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
115625INTER-REGIONAL TRANSFER14/03/2024 11:49:03 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

At 2307 hrs 14/03/2024 there was an unplanned outage of Robertstown - Tungkillo No. 1 275 kV Line.


The following constraint set(s) invoked at 2315 hrs 14/03/2024
S-RBTU

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
115618INTER-REGIONAL TRANSFER14/03/2024 07:32:14 AM

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

At 0800 hrs 14/03/2024 there was a short notice outage of Lismore 132kV SVC.

The following constraint set(s) invoked at 0800 hrs 14/03/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
115592RESERVE NOTICE11/03/2024 06:21:48 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 11/03/2024 to 2030 hrs 11/03/2024.
The forecast capacity reserve requirement is 469 MW.
The minimum capacity reserve available is 402 MW.


Manager NEM Real Time Operations
     
115589RESERVE NOTICE11/03/2024 07:21:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115588 is cancelled at 0717 hrs 11/03/2024.

Manager NEM Real Time Operations
     
115588RESERVE NOTICE11/03/2024 05:26:01 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115587 has been updated at 0520 hrs to the following:

[1.] From 1930 hrs 11/03/2024 to 2000 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.

Manager NEM Real Time Operations
     