116563MARKET SYSTEMS09/05/2024 03:10:22 PM

CHG0089532 | Cancelled | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Change Number: CHG0089532

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     
116560MARKET SYSTEMS09/05/2024 11:07:46 AM

CHG0089539 | Production | QLD Internet Router Refresh

Change Number: CHG0089539

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Internet Access

Change Title: QLD Internet Router Refresh

Change Start Date & Time: 25/05/2024 09:00:08 AEST
Change End Date & Time: 25/05/2024 14:00:08 AEST
Outage Start Date & Time: 25/05/2024 09:30:21 AEST
Outage End Date & Time: 25/05/2024 13:00:21 AEST

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only

SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.

GASHUB: No impact is expected as GASHUB is currently operating out of NOR Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116551SETTLEMENTS RESIDUE08/05/2024 08:30:22 PM

[EventId:202405082030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 20:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2030 hrs on 8 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Refer to market notice: 116542

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 8 May 2024.

This is an AEMO autogenerated Market Notice.
     
116543INTER-REGIONAL TRANSFER08/05/2024 03:50:23 PM

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.

The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116542SETTLEMENTS RESIDUE08/05/2024 03:30:23 PM

[EventId:202405081530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 8 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 8 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
116525INTER-REGIONAL TRANSFER08/05/2024 12:11:09 PM

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.

The outage has been cancelled at 1154 hrs 08/05/2024

Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1

Manager NEM Real Time Operations
     
116524SETTLEMENTS RESIDUE08/05/2024 08:30:23 AM

[EventId:202405080830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 08:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 8 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Refer to market notice: 116521

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0830 hrs on 8 May 2024.

This is an AEMO autogenerated Market Notice.
     
116521SETTLEMENTS RESIDUE08/05/2024 06:35:22 AM

[EventId:202405080635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 06:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0635 hrs on 8 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0635 hrs on 8 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
116515SETTLEMENTS RESIDUE07/05/2024 07:30:20 PM

[EventId:202405071930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 May 2024 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 7 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2024.

Refer to market notice: 116512

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 7 May 2024.