Market Notices

72310MARKET INTERVENTION04/01/2020 04:18:46 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 04/01/2020

Refer to AEMO Electricity Market Notice no. 72297.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
16:30 to 22:00 hrs 04/01/2020
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
72301MARKET INTERVENTION04/01/2020 04:06:11 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 04/01/2020

Refer to AEMO Electricity Market Notice no. 72297.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
17:00 to 00:00 hrs 05/01/2020
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
72300MARKET INTERVENTION04/01/2020 04:06:25 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 04/01/2020

Refer to AEMO Electricity Market Notice no. 72297.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
17:00 to 00:00 hrs 05/01/2020
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations