88780RECLASSIFY CONTINGENCY23/07/2021 05:48:15 PM

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV

Duration: 23/07/2021 17:48 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
88779PRICES SUBJECT TO REVIEW23/07/2021 05:45:13 PM

[EventId:202107231750_review] Prices for interval 23-Jul-2021 17:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 23 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-Jul-2021 17:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88777PRICES SUBJECT TO REVIEW23/07/2021 05:40:17 PM

[EventId:202107231745_review] Prices for interval 23-Jul-2021 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 23 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-Jul-2021 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88776RECLASSIFY CONTINGENCY24/07/2021 12:13:06 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 0015 hrs 24/07/2021 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
88775RECLASSIFY CONTINGENCY24/07/2021 12:14:01 AM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 0015 hrs 24/07/2021 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
88774PRICES SUBJECT TO REVIEW23/07/2021 05:35:17 PM

[EventId:202107231740_review] Prices for interval 23-Jul-2021 17:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 23 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-Jul-2021 17:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88773PRICES SUBJECT TO REVIEW23/07/2021 05:30:15 PM

[EventId:202107231735_review] Prices for interval 23-Jul-2021 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 23 July 2021

PRICES ARE SUBJECT TO REVIEW for dispatch interval 23-Jul-2021 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
88771RESERVE NOTICE23/07/2021 05:21:51 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld region on 23/07/2021.

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 88770 has been updated at 1720 hrs to the following:
From 1930 hrs to 2130 hrs 23/07/2021.
The contingency forecast capacity reserve requirementd is 1061 MW.
The minimum capacity reserve available is 751 MW.

Manager NEM Real Time Operations
88770RESERVE NOTICE23/07/2021 04:04:57 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Qld region on 23/07/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period:

From 1930 hrs to 2100 hrs 23/07/2021.
The forecast capacity reserve requirement is 1043 MW.
The minimum capacity reserve available is 963 MW.

Manager NEM Real Time Operations