Market Notices

88971GENERAL NOTICE27/07/2021 07:04:10 AM

Non-credible contingency event more likely to occur due to existence of abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event is more likely to occur because of the existence of abnormal conditions namely severe weather in the SA region.

As at the time of this notice the criteria for reclassification of any non-credible contingency event have not been met, however there is a possibility of severe weather impacting multiple transmission elements in its vicinity.

Conditions can change rapidly and potentially impacted plant may change. Further notices will only be published to advise of any reclassification, or when the abnormal conditions have ceased to impact the likelihood of a non-credible event occurring.

Constraint set I-VS_250 invoked at 0705 hrs 27/07/2021 until further notice.

Manager NEM Real Time Operations
88970RECLASSIFY CONTINGENCY27/07/2021 12:13:52 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 0010 hrs 27/07/2021 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
88969RECLASSIFY CONTINGENCY27/07/2021 12:12:21 AM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 0010 hrs 27/07/2021 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
88968RESERVE NOTICE26/07/2021 07:13:41 PM

Cancellation of Actual (LOR1) condition in the QLD region - 26/07/2021

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 26/07/2021

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No 88967 is cancelled at 1900 hrs 26/07/2021

Manager NEM Real Time Operations
88967RESERVE NOTICE26/07/2021 06:18:44 PM

Actual Lack Of Reserve Level 1 (LOR1) in the Qld region - 26/07/2021

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the Qld region - 26/07/2021

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the Qld region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The capacity reserve requirement is 923 MW

The minimum capacity reserve available is 845 MW

Manager NEM Real Time Operations
88966RESERVE NOTICE26/07/2021 05:53:50 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Qld region on 26/07/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period:

From 1800 hrs to 1900 hrs 26/07/2021.
The forecast capacity reserve requirement is 1024 MW.
The minimum capacity reserve available is 969 MW.

Manager NEM Real Time Operations
88965RESERVE NOTICE26/07/2021 05:15:50 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld region on 26/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 88964 is cancelled at 1715 hrs 26/07/2021.

Manager NEM Real Time Operations
88964RESERVE NOTICE26/07/2021 04:41:00 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Qld region on 26/07/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Qld region for the following period:

From 1800 hrs to 1900 hrs 26/07/2021.
The forecast capacity reserve requirement is 1076 MW.
The minimum capacity reserve available is 1067 MW.

Manager NEM Real Time Operations
88963NON-CONFORMANCE26/07/2021 04:15:50 PM

NON-CONFORMANCE Region QLD1 Monday, 26 July 2021

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 26 July 2021

AEMO declared a schedule generating unit non-conforming

Unit: Tarong3
Duration: 26/07/2021 16:05 to 26/07/2021 16:10
Amount: 9 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations