115805GENERAL NOTICE26/03/2024 08:15:10 AM

Cancellation - Severe Space Weather Watch Notification 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Severe Space Weather Watch Notification 25/03/2024

Refer to MN 115774

The Australian Bureau of Meteorology's Space Weather forecasting centre has cancelled the following notification.

Severe space weather watch: A recent Coronal Mass Ejection associated with a solar flare is anticipated to impact the Earth within the next 48 hours.


Manager NEM Real Time Operations
115794POWER SYSTEM EVENTS25/03/2024 03:48:06 PM

Non-credible contingency event - SA region - Torrens Island 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - Torrens Island 25/03/2024

At 1412 hrs there was an unplanned outage of the following elements:
Torrens Island BW3 275 kV CB
Torrens Island BC3 275 kV CB
Torrens Island - Lefevre 275 kV line

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
115783POWER SYSTEM EVENTS25/03/2024 02:17:51 PM

Update - Non-credible contingency event - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 25/03/2024

Refer AEMO Electricity Market Notice 115777

At 1350 hrs the Davenport - Brinkworth 275 kV line, Brinkworth No 3 275/132 kV transformer
and Brinkworth - Templers West 275 kV line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
115778INTER-REGIONAL TRANSFER25/03/2024 09:43:59 AM

Inter-regional transfer limit variation - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - SA region - 25/03/2024

Refer market notice: 115777

At 0810 hrs 25/03/2024 there was an unplanned outage of elements:

Davenport - Brinkworth 275 kV line
Brinkworth No 3 275/132 kV transformer
Brinkworth - Templers West 275 kV line

Constraint set(s) invoked: S-X_DVBR+BRTW+TWPA


This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115777POWER SYSTEM EVENTS25/03/2024 09:27:07 AM

Non-credible contingency event - SA region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 25/03/2024

At 0810 hrs there was an unplanned outage of the following elemets:
Davenport - Brinkworth 275 kV line
Brinkworth No 3 275/132 kV transformer
Brinkworth - Templers West 275 kV line

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115775INTER-REGIONAL TRANSFER25/03/2024 06:49:58 AM

Inter-regional transfer limit variation - Armidale - Uralla 8U 330 kV line - NSW region - 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Uralla 8U 330 kV line - NSW region - 25/03/2024

A planned outage of Armidale - Uralla 8U 330 kV line in the NSW region was scheduled from 0500 hrs 25/03/2024 to 1500 hrs 25/03/2024.

The outage has been returned to service at 0645 hrs 25/03/2024.

Constraint set(s) revoked:
N-ARUL_8U
N-TW_SVC
N-X_8U+DM+TW_SVC
N-MORBOR

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115774GENERAL NOTICE25/03/2024 04:33:09 AM

Severe Space Weather Watch Notification 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Severe Space Weather Watch Notification 25/03/2024

The Australian Bureau of Meteorology's Space Weather Forecasting Centre has issued the following notification.

Severe space weather watch: A recent space weather event is anticipated to impact the Earth within the next 48 hours.

The effects are expected to be significant.

Increased awareness of critical infrastructure is advised.

Please monitor the SWS website for further updates at https://www.sws.bom.gov.au

If required; actions will be taken as per AEMO's system operating procedure SO_OP3715 Power System Security Guidelines.

Manager NEM Real Time Operations
115772INTER-REGIONAL TRANSFER24/03/2024 04:47:46 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 cable of Directlink.

The following constraint set was invoked at 1640 hrs 24/03/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115771POWER SYSTEM EVENTS24/03/2024 04:39:39 PM

Update - Non-credible contingency event - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 14/03/2024

Refer AEMO Electricity Market Notice 115624

At 1635 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.