NON-CONFORMANCE Region VIC1 Saturday, 2 March 2024
NON-CONFORMANCE VIC1 Region Saturday, 2 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GLRWNSF1
Duration: 02/03/2024 13:45 to 02/03/2024 13:55
Amount: 110 MW
Constraint: NC-V_GLRWNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 2 March 2024
NON-CONFORMANCE QLD1 Region Saturday, 2 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 02/03/2024 07:55 to 02/03/2024 08:05
Amount: 21 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115374 is cancelled at 1900 hrs 29/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1001 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 29/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115370 is cancelled at 1545 hrs 29/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 29/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1500 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1066 MW
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 28/02/2024
Non-credible contingency event - QLD region - 28/02/2024
At 1029 hrs the Tully - Cardwell No.7389 132 kV Line tripped and auto reclosed and Ross - Woree No. 8905 275 kV Line tripped and auto reclosed.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 26 February 2024
NON-CONFORMANCE QLD1 Region Monday, 26 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 26/02/2024 23:10 to 26/02/2024 23:15
Amount: -32 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 26/02/2024
Cancellation of Actual (LOR1) condition in the QLD region - 26/02/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No. 115160 is cancelled at 1940 hrs 26/02/2024.
Manager NEM Real Time Operations