Filter by category
Filter by Date
Network Augmentation Commissioned - QLD Region - 01/06/2024
Network Augmentation Commissioned - QLD Region - 01/06/2024
H90 Tully South 275 kV Switching Station has been cut into the existing Ross - Woree No.8905 275 kV line to form the following circuits:
H13 Ross - H90 Tully South No.8905/1 275 kV line
H90 Tully South - H39 Woree No.8905/2 275 kV line
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 1 June 2024
NON-CONFORMANCE VIC1 Region Saturday, 1 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS2
Duration: 01/06/2024 07:25 to 01/06/2024 07:40
Amount: -8 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202405311140_review] Prices for interval 31-May-2024 11:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311135_review] Prices for interval 31-May-2024 11:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311130_review] Prices for interval 31-May-2024 11:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311125_review] Prices for interval 31-May-2024 11:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311120_review] Prices for interval 31-May-2024 11:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405311115_review] Prices for interval 31-May-2024 11:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1110 hrs on 31 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-May-2024 11:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Sheffield - Georgetown No. 2 220 kV line - TAS region - 30/05/2024
Inter-regional transfer limit variation -Sheffield - Georgetown No. 2 220 kV line - TAS region - 30/05/2024
At 2301 hrs 30/05/2024 there was an unplanned outage of Sheffield - Georgetown No. 2 220 kV line
The following constraint set(s) invoked at 2310 hrs 30/05/2024
T-GTSH
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations