Cancellation - Variation to FCAS Lower regulation requirements for Mainland Regulation - 13 Oct 2016
Cancellation - Variation to FCAS Lower regulation requirements for Mainland Regulation - 13/10/2016.
The FCAS Lower regulation requirement was increased to manage time error to within standards.
The following constraint was applied to increase the lower regulation requirements being dispatched
F-MAIN_LREG_0400 invoked from 0730 hrs to 0830 hrs.
Manager NEM Real Time Operations
Variation to FCAS Lower regulation requirements for Mainland Regulation - 13 Oct 2016
Variation to FCAS Lower regulation requirements for Mainland Regulation - 13/10/2016.
The FCAS Lower regulation requirement was increased to manage time error to within standards.
The following constraint was invoked to increase the lower regulation requirements being dispatched
F-MAIN_LREG_0400 invoked from 0730 hrs.
Manager NEM Real Time Operations
Update - Planned outage of Heywood to South East No.2 275kV line in South Australia and Victoria regions starting on 18/10/2016 0700hrs
Update to Market Notice 54934
This market notice is FOR INFORMATION ONLY.
An outage of Heywood to South East No.2 275 kV line in South Australia and Victoria regions was previously planned from 0700 hrs on 18 October 2016 to 1700 hrs on 20 October 2016. The planned end time of this outage has been revised to 1700hrs on 22/10/2016.
During this outage, Heywood 500/275 kV M2 transformer will be off-loaded.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-I-HYSE (includes F-S_LREG_0035 and F-S_RREG_0035)
I-HYSE
S-X_BC_CP
V-HYTX_M12
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Kin Onn Wong
AEMO Operations
Planned outage of Heywood to Mortlake PS 500kV line in Victoria region from 09/11/2016 0600 hrs to 09/11/2016 1600 hrs
This market notice is FOR INFORMATION ONLY.
The Heywood to Mortlake PS 500kV line in Victoria Region is planned out of service from 0600 hrs on 9 November 2016 to 1600 hrs on 9 November 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-HYMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-X_BC_CP
V-HYMO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Heywood to Mortlake PS 500kV line in Victoria region from 08/11/2016 0600 hrs to 08/11/2016 1600 hrs
This market notice is FOR INFORMATION ONLY.
The Heywood to Mortlake PS 500kV line in Victoria Region is planned out of service from 0600 hrs on 8 November 2016 to 1600 hrs on 8 November 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-HYMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-X_BC_CP
V-HYMO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Heywood No.2 500kV Bus in Victoria region from 08/11/2016 1600 hrs to 09/11/2016 0600 hrs
This market notice is FOR INFORMATION ONLY.
The Heywood No.2 500 kV busbar in Victoria Region is planned out of service from 1600 hrs on 8 November 2016 to 0600 hrs on 9 November 2016. During this outage, Heywood 500/275 kV M2 transformer will be off-loaded and Heywood - Mortlake - Alcoa Portland No.2 500 kV line will be opened at Heywood.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-I_HYSE (includes F-S_LREG_0035 and F-S_RREG_0035)
S-X_BC_CP
V-HYTX_M12
V-HY_500BUS
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Cancellation of Planned outage of Heywood to South East No.1 275kV line from 11/10/2016 0700 hrs to 13/10/2016 1700 hrs
Cancellation of the following planned outage in South Australia and Victoria regions:
The Heywood to South East No.1 275 kV line, originally planned out of service from 0700 hrs on 11/10/2016 to 1700 hrs on 13/10/2016 has now been cancelled.
Refer to Market Notice 54893.
Harmohan Singh
AEMO Operations
Cancellation - Variation to FCAS Lower regulation requirements for Mainland Regulation - 4 Oct 2016
Refer ELECTRICITY MARKET NOTICE 55183
Variation to FCAS Lower regulation requirements for Mainland Regulation 04/10/2016.
The FCAS Lower regulation requirement was increased to manage time error to within standards.
The following constraint was invoked to increase the lower regulation requirements being dispatched in Vic, NSW and QLD.
#LR_20161004084741 revoked at 0920 hrs.
Manager NEM Real Time Operations
Variation to FCAS Lower regulation requirements for Mainland Regulation - 4 Oct 2016
Variation to FCAS Lower regulation requirements for Mainland Regulation 04/10/2016.
The FCAS Lower regulation requirement was increased to manage time error to within standards.
The following constraint was invoked to increase the lower regulation requirements being dispatched in Vic, NSW and QLD.
#LR_20161004084741 invoked from 0850 hrs.
Manager NEM Real Time Operations