116507INTER-REGIONAL TRANSFER07/05/2024 02:31:38 PM

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024

A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.

The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.

Constraint set(s) invoked: N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116503RESERVE NOTICE07/05/2024 12:01:42 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.

No LOR2 condition is currently forecast in the STPASA period.


AEMO Operations
     
116502RESERVE NOTICE07/05/2024 10:02:31 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

     
116419PRICES SUBJECT TO REVIEW02/05/2024 08:50:18 AM

[EventId:202405020855_review] Prices for interval 02-May-2024 08:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0850 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116418PRICES SUBJECT TO REVIEW02/05/2024 08:45:17 AM

[EventId:202405020850_review] Prices for interval 02-May-2024 08:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116417PRICES SUBJECT TO REVIEW02/05/2024 08:40:23 AM

[EventId:202405020845_review] Prices for interval 02-May-2024 08:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0840 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116416PRICES SUBJECT TO REVIEW02/05/2024 08:35:19 AM

[EventId:202405020840_review] Prices for interval 02-May-2024 08:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0835 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116415PRICES SUBJECT TO REVIEW02/05/2024 08:30:18 AM

[EventId:202405020835_review] Prices for interval 02-May-2024 08:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0830 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116414PRICES SUBJECT TO REVIEW02/05/2024 08:25:14 AM

[EventId:202405020830_review] Prices for interval 02-May-2024 08:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0825 hrs on 2 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     