112179RESERVE NOTICE11/12/2023 01:37:21 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
112170RECLASSIFY CONTINGENCY11/12/2023 07:44:18 AM

Update - Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 11/12/2023

Refer AEMO Electricity Market Notice 112165

Region: SA

The following constraint set(s) invoked:
Initially S-MNWT and S-MN_0 then replaced with S-BR_MN+MN_WT

This constraint set(s) contains equations with the following interconnectors on the LHS:
V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.


Manager NEM Real Time Operations
112161RECLASSIFY CONTINGENCY10/12/2023 03:45:45 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 10/12/2023 15:45 hrs until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
112156RECLASSIFY CONTINGENCY10/12/2023 12:30:18 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 10/12/2023 12:30 hrs until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
112155RECLASSIFY CONTINGENCY09/12/2023 10:59:35 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 09/12/2023 22:59

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 112136

Auto-generated on behalf of Manager NEM Real Time Operations
112151PRICES UNCHANGED09/12/2023 06:30:50 PM

[EventId:202312091805_confirmed] Prices for interval 09-Dec-2023 18:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023

PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:05.

In accordance with Market Notice 112141 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112150PRICES UNCHANGED09/12/2023 06:29:29 PM

[EventId:202312091825_confirmed] Prices for interval 09-Dec-2023 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023

PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:25.

In accordance with Market Notice 112145 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112149PRICES UNCHANGED09/12/2023 06:27:36 PM

[EventId:202312091820_confirmed] Prices for interval 09-Dec-2023 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023

PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:20.

In accordance with Market Notice 112144 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
112148PRICES UNCHANGED09/12/2023 06:28:31 PM

[EventId:202312091815_confirmed] Prices for interval 09-Dec-2023 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 9 December 2023

PRICES ARE NOW CONFIRMED for trading interval 09-Dec-2023 18:15.

In accordance with Market Notice 112143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.