114012MARKET SYSTEMS30/01/2024 01:47:21 PM

CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Pre-Production MSATS r50.0.5 Patch Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
114008GENERAL NOTICE30/01/2024 10:33:16 AM

NEM Local Temperature Alerts for SA from 30 Jan 2024 to 03 Feb 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 3rd Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
113998RESERVE NOTICE29/01/2024 08:23:46 PM

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113994 is cancelled at 2000 hrs 29/01/2024.

Manager NEM Real Time Operations
113994RESERVE NOTICE29/01/2024 06:12:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1810 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1197 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations
113958RESERVE NOTICE29/01/2024 09:17:19 AM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:

1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.

2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.

AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.

AEMO Operations
113892RESERVE NOTICE27/01/2024 08:46:54 PM

Cancellation of Actual (LOR1) condition in the QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 27/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113871 is cancelled at 2045 hrs 27/01/2024.

Manager NEM Real Time Operations
113871RESERVE NOTICE27/01/2024 06:27:46 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 27/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 664 MW.

Manager NEM Real Time Operations
113748MARKET SYSTEMS25/01/2024 03:26:29 PM

CHG0082787 | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release

Change Start Date & Time: 30/01/2024 12:00:00 AEST
Change End Date & Time: 30/01/2024 17:00:00 AEST
Outage Start Date & Time: 30/01/2024 12:00:00 AEST
Outage End Date & Time: 30/01/2024 14:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
113731GENERAL NOTICE25/01/2024 10:49:36 AM

NEM Local Temperature Alerts for NSW, QLD, SA from 25 Jan 2024 to 29 Jan 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

NSW
Sydney Observatory Hill (39+ Deg C): 26th Jan

QLD
Dalby Ap (37+ Deg C): 25th Jan, 26th Jan, 27th Jan

SA
Port Augusta Ap (39+ Deg C): 29th Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm