[EventId:202106131800_review] Prices for interval 13-Jun-2021 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202106131755_review] Prices for interval 13-Jun-2021 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202106131750_review] Prices for interval 13-Jun-2021 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202106131745_review] Prices for interval 13-Jun-2021 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202106131740_review] Prices for interval 13-Jun-2021 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202106131735_review] Prices for interval 13-Jun-2021 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 13 June 2021
PRICES ARE SUBJECT TO REVIEW for dispatch interval 13-Jun-2021 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/06/2021
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0730 hrs 16/06/2021 to 0800 hrs 16/06/2021
The forecast capacity reserve requirement is 1403 MW
The minimum capacity reserve available is 1270 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation - Psymetrix PhasorPoint - Unplanned Outage - 13/06/2021
Refer AEMO Electricity Market Notice 87043
AEMO Psymetrix PhasorPoint application returned to service.
The following constraint set was invoked from 1220 hrs to 1255 hrs
I-OSC_STAB_MON
The constraint set contains the following interconnectors on the left hand side.
NSW1-QLD1
V-S_MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
Psymetrix PhasorPoint - Unplanned Outage - 13/06/2021
There is an unplanned outage of AEMO Psymetrix PhasorPoint application.
The following constraint set was invoked at 1220 hrs 13/06/2021
I-OSC_STAB_MON
The constraint set contains the following interconnectors on the left hand side.
NSW1-QLD1
V-S_MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations