CHG0090782 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 26/06/2024 09:00:00 AEST
Change End Date & Time: 26/06/2024 22:00:00 AEST
Outage Start Date & Time: 26/06/2024 18:30:00 AEST
Outage End Date & Time: 26/06/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024
Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024
A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.
The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024
Constraint set revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
CHG0090106 | Cancelled | Production | Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Update - Non-credible contingency event - VIC region - 18/06/2024
Update - Non-credible contingency event - VIC region - 18/06/2024
Refer AEMO Electricity Market Notice 117042
The cause of this non credible contingency event is not known at this stage..
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: VIC
Elements: Glenrowan No1 66kV Bus
Duration: 0903 hrs 18/06/2024 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region QLD1 Monday, 17 June 2024
NON-CONFORMANCE QLD1 Region Monday, 17 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 17/06/2024 04:30 to 17/06/2024 05:25
Amount: -51 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Refer Market Notice 116996
AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.
Manager NEM Real Time Operations