84889MARKET INTERVENTION30/04/2021 01:59:22 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

Refer Market Notice 84859

The synchronous generating units expected to be synchronised in SA from 0000 hrs 01/05/2021 to 1700 hrs 01/05/2021 in Pre-dispatch published at 1330 hrs 30/04/2021 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1800 hrs 30/04/2021, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
84888RECLASSIFY CONTINGENCY30/04/2021 01:24:25 PM

Reclassification of a Non-Credible Contingency Event: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV line and Strathmore-Clare South 7208 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV and Strathmore-Clare South 7208 132kV

Duration: 30/04/2021 13:24 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
84887RECLASSIFY CONTINGENCY30/04/2021 01:24:25 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 30/04/2021 13:24 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
84886MARKET INTERVENTION30/04/2021 03:01:55 PM

Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 29/04/2021

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 29/04/2021

Refer Market Notice 84858

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs 30/04/2021

Manager NEM Real Time Operations
84884PRICES UNCHANGED30/04/2021 09:07:35 AM

[EventId:202104300840_confirmed] Prices for interval 30-Apr-2021 08:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 30 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 30-Apr-2021 08:40.

In accordance with Market Notice 84874 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
84883PRICES UNCHANGED30/04/2021 09:06:27 AM

[EventId:202104300900_confirmed] Prices for interval 30-Apr-2021 09:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 30 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 30-Apr-2021 09:00.

In accordance with Market Notice 84878 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
84882PRICES UNCHANGED30/04/2021 09:04:50 AM

[EventId:202104300855_confirmed] Prices for interval 30-Apr-2021 08:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 30 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 30-Apr-2021 08:55.

In accordance with Market Notice 84877 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
84881PRICES UNCHANGED30/04/2021 09:03:27 AM

[EventId:202104300850_confirmed] Prices for interval 30-Apr-2021 08:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 30 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 30-Apr-2021 08:50.

In accordance with Market Notice 84876 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
84880PRICES UNCHANGED30/04/2021 09:02:15 AM

[EventId:202104300845_confirmed] Prices for interval 30-Apr-2021 08:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 30 April 2021

PRICES ARE NOW CONFIRMED for dispatch interval 30-Apr-2021 08:45.

In accordance with Market Notice 84875 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.