Market Notices

53538GENERAL NOTICE27/05/2016 12:43:22 AM

Cancellation - Brisbane Communication Issues - 27th May 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Brisbane Communication Issues - 27th May 2016

Refer to MN 53535

This is to advise that the problems on the AEMO Brisbane Control Centre Phone system have been resolved.

Participants may noiw use normal Brisbane Control Centre and Sydney Control Centre contact numbers.

Manager NEM Real Time Operations
53535GENERAL NOTICE27/05/2016 12:17:22 AM

Brisbane Communication Issues - 27th May 2016

AEMO ELECTRICITY MARKET NOTICE

Brisbane Communication Issues - 27th May 2016

This is to advise that problems exist on the AEMO Brisbane Control Centre Phone system.

Participants who normally communicate with the Brisbane Control Centre are advised to utilise the backup telephone numbers or the alternative Sydney Control Centre contact numbers.

Further information will be provided when the problem is rectified.

Manager NEM Real Time Operations
53534NON-CONFORMANCE26/05/2016 11:20:53 PM

NON-CONFORMANCE Region VIC1 -26 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region - 26 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: BDL02
Duration: 26/05/2016 23:05 to 26/05/2016 23:10
Amount: -35 MW
Constraint: NC-V_BDL02

Manager NEM Real Time Operations
53524NON-CONFORMANCE26/05/2016 08:30:14 AM

NON-CONFORMANCE Region QLD1 Thursday, 26 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 26 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: BRAEMAR3
Duration: 26/05/2016 08:20 to 26/05/2016 08:30
Amount: -36 MW
Constraint: NC-Q_BRAEMAR3

Auto-generated on behalf of Manager NEM Real Time Operations
53517NON-CONFORMANCE25/05/2016 12:25:17 AM

NON-CONFORMANCE Region VIC1 Wednesday, 25 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 25 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: YWPS2
Duration: 25/05/2016 00:00 to 25/05/2016 00:25
Amount: -27 MW
Constraint: NC-V_YWPS2

Auto-generated on behalf of Manager NEM Real Time Operations
53504GENERAL NOTICE23/05/2016 04:50:14 PM

Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 and 30 May 2016

AEMO ELECTRICITY MARKET NOTICE.


Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 May and 30 May 2016.

There are planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line between 0630-1630hrs on 25 May 2016 and 0630-1800hrs on 30 May 2016.

During these outages, South Australia region remains connected to the NEM for the first contingency (trip of the Moorabool - Sydenham No.2 500 kV line). However, there is a potential risk of South Australia region separation from the rest of the NEM for the subsequent contingency following the first contingency.

AEMO will invoke the following FCAS regulation constraint sets after the first contingency during this outage to secure the power system in South Australia region.

F-S_LREG_0035
F-S_RREG_0035

Refer to AEMO Network Outage Schedule (NOS) for further details


Operations Planning
53501NON-CONFORMANCE23/05/2016 08:30:14 AM

NON-CONFORMANCE Region NSW1 Monday, 23 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 23 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: SITHE01
Duration: 23/05/2016 06:35 to 23/05/2016 08:30
Amount: 23 MW
Constraint: NC-N_SITHE01

Auto-generated on behalf of Manager NEM Real Time Operations
53487NON-CONFORMANCE23/05/2016 05:10:14 AM

NON-CONFORMANCE Region SA1 Monday, 23 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 23 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: WATERLWF
Duration: 23/05/2016 03:35 to 23/05/2016 05:10
Amount: 107 MW
Constraint: NC-S_WATERLWF

Auto-generated on behalf of Manager NEM Real Time Operations
53481NON-CONFORMANCE23/05/2016 04:30:15 AM

NON-CONFORMANCE Region VIC1 Monday, 23 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 23 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: HWPS3
Duration: 23/05/2016 04:20 to 23/05/2016 04:30
Amount: 11 MW
Constraint: NC-V_HWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm