Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 77532
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 0005 hrs. 06/09/2020
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0000 hrs 06/09/2020.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Direction - SA region - 05/09/2020
Direction - SA region - 05/09/2020
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1635 hrs 05/09/2020.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units expected to be synchronised in SA from 0930hrs 06/09/2020 to 1630hrs 06/09/2020 in Pre-dispatch published at 1400hrs 05/09/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 1630hrs 05/09/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (Vic) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 1015 hrs
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 04/09/2020 20:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 77526
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 04/09/2020 18:50 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202009041610_confirmed] Prices for interval 04-Sep-2020 16:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 4 September 2020
PRICES ARE NOW CONFIRMED for dispatch interval 04-Sep-2020 16:10.
In accordance with Market Notice 77511 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202009041630_confirmed] Prices for interval 04-Sep-2020 16:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 4 September 2020
PRICES ARE NOW CONFIRMED for dispatch interval 04-Sep-2020 16:30.
In accordance with Market Notice 77519 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.