Market Notices

112916NON-CONFORMANCE30/12/2023 01:05:12 PM

NON-CONFORMANCE Region NSW1 Saturday, 30 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 30 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NEWENSF2
Duration: 30/12/2023 12:50 to 30/12/2023 13:05
Amount: 163 MW
Constraint: NC-N_NEWENSF2

Auto-generated on behalf of Manager NEM Real Time Operations
112818NON-CONFORMANCE27/12/2023 02:45:22 PM

NON-CONFORMANCE Region NSW1 Wednesday, 27 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 27 December 2023

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 27/12/2023 14:35 to 27/12/2023 14:45
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
112793POWER SYSTEM EVENTS27/12/2023 12:04:43 AM

Non-credible contingency event - QLD region - 26/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 26/12/2023

At 2345 hrs the Strathmore Clare South 7208 and the Strathmore Clare South Tee King Creek 7128 132kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
112599NON-CONFORMANCE22/12/2023 03:35:19 PM

NON-CONFORMANCE Region QLD1 Friday, 22 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 22 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-2
Duration: 22/12/2023 15:30 to 22/12/2023 15:35
Amount: 10 MW
Constraint: NC-Q_STAN-2

Auto-generated on behalf of Manager NEM Real Time Operations
112591NON-CONFORMANCE22/12/2023 01:10:14 PM

NON-CONFORMANCE Region QLD1 Friday, 22 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 22 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OAKEY2SF
Duration: 22/12/2023 13:00 to 22/12/2023 13:10
Amount: 54 MW
Constraint: NC-Q_OAKEY2SF

Auto-generated on behalf of Manager NEM Real Time Operations
112579POWER SYSTEM EVENTS21/12/2023 03:12:07 PM

Non-credible contingency event - QLD region - 21/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 21/12/2023

At 1424 hrs the H14 Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No.3 275/110 kV transformers.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
112516NON-CONFORMANCE19/12/2023 11:10:16 AM

NON-CONFORMANCE Region VIC1 Tuesday, 19 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 19 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS2
Duration: 19/12/2023 11:00 to 19/12/2023 11:10
Amount: 19 MW
Constraint: NC-V_YWPS2

Auto-generated on behalf of Manager NEM Real Time Operations
112485RESERVE NOTICE18/12/2023 12:19:11 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112483 is cancelled at 1100 hrs 18/12/2023.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
112483RESERVE NOTICE18/12/2023 05:03:52 AM

STPASA - Update to the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/12/2023

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112471 has been updated at 0500 hrs 18/12/2023 to the following:

From 1230 hrs 19/12/2023 to 1600 hrs 19/12/2023.
The forecast capacity reserve requirement is 1071 MW.
The minimum capacity reserve available is 42 MW.

AEMO is seeking a market response.

AEMO estimates that the latest time at which permission can be given for a planned outage to proceed is 0530 hrs on 19/12/2023.

Manager NEM RTO
X