Market Notices

74240RECLASSIFY CONTINGENCY17/02/2020 10:50:41 PM

Reclassification of a Non-Credible Contingency Event: Condabri North - Condabri Central No. 7400 and Condabri North - Condabri Central No. 7401 132kV lines in QLD due to lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Condabri North - Condabri Central No.7400 132kV and Condabri North - Condabri Central No. 7401 132 kV

Duration: 17/02/2020 22:46 hrs until further notice

Constraint set(s) invoked:
NONE

Manager NEM Real Time Operations
74239RECLASSIFY CONTINGENCY17/02/2020 10:46:45 PM

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV

Duration: 17/02/2020 22:46 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74238RECLASSIFY CONTINGENCY17/02/2020 10:09:20 PM

Cancellation of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV

Cancellation time: 17/02/2020 22:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74236

Auto-generated on behalf of Manager NEM Real Time Operations
74237RECLASSIFY CONTINGENCY17/02/2020 09:41:04 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 and Wollar - Mt Piper No.5A5 500kV lines in NSW due to lightning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to lightning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW

Lines: Bayswater - Mt Piper No.5A3 and Wollar - Mt Piper No.5A5 500kV lines

Cancellation time: 2140 hrs 17/02/2020
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 74184

Manager NEM Real Time Operations
74236RECLASSIFY CONTINGENCY17/02/2020 07:51:55 PM

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV

Duration: 17/02/2020 19:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74235MARKET INTERVENTION17/02/2020 07:22:01 PM

Cancellation - Direction Vic region 01/02/2020

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Direction Vic region 01/02/2020

Refer Market Notice 73338

The AEMO Intervention Event and all associated directions was cancelled from 1735 hrs 17/02/2020.

Manager NEM Real Time Operations
74234RECLASSIFY CONTINGENCY17/02/2020 06:55:10 PM

Cancellation of a Non-Credible Contingency Event: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV line and Goonyella - Newlands No. 7155 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV and Goonyella - Newlands No. 7155 132 kV

Cancellation time: 17/02/2020 18:55

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74200

Auto-generated on behalf of Manager NEM Real Time Operations
74233RECLASSIFY CONTINGENCY17/02/2020 06:55:10 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 17/02/2020 18:55

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74196

Auto-generated on behalf of Manager NEM Real Time Operations
74232RECLASSIFY CONTINGENCY17/02/2020 06:55:20 PM

Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Cancellation time: 17/02/2020 18:55

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74199

Auto-generated on behalf of Manager NEM Real Time Operations