Market Notices

112613INTER-REGIONAL TRANSFER23/12/2023 06:39:17 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023


A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.

The outage has been cancelled.

The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112599NON-CONFORMANCE22/12/2023 03:35:19 PM

NON-CONFORMANCE Region QLD1 Friday, 22 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 22 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-2
Duration: 22/12/2023 15:30 to 22/12/2023 15:35
Amount: 10 MW
Constraint: NC-Q_STAN-2

Auto-generated on behalf of Manager NEM Real Time Operations
112591NON-CONFORMANCE22/12/2023 01:10:14 PM

NON-CONFORMANCE Region QLD1 Friday, 22 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 22 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OAKEY2SF
Duration: 22/12/2023 13:00 to 22/12/2023 13:10
Amount: 54 MW
Constraint: NC-Q_OAKEY2SF

Auto-generated on behalf of Manager NEM Real Time Operations
112590INTER-REGIONAL TRANSFER22/12/2023 01:01:28 PM

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.

Constraint set(s) invoked: T-HAPM_220


This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112579POWER SYSTEM EVENTS21/12/2023 03:12:07 PM

Non-credible contingency event - QLD region - 21/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 21/12/2023

At 1424 hrs the H14 Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No.3 275/110 kV transformers.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
112516NON-CONFORMANCE19/12/2023 11:10:16 AM

NON-CONFORMANCE Region VIC1 Tuesday, 19 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 19 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS2
Duration: 19/12/2023 11:00 to 19/12/2023 11:10
Amount: 19 MW
Constraint: NC-V_YWPS2

Auto-generated on behalf of Manager NEM Real Time Operations
112433INTER-REGIONAL TRANSFER17/12/2023 06:09:07 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0600 hrs 17/12/2023

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for return to service details

Manager NEM Real Time Operations
112432INTER-REGIONAL TRANSFER17/12/2023 05:48:19 AM

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.

Constraint set(s) invoked: N-SWVY_29

The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112282NON-CONFORMANCE13/12/2023 11:48:48 PM

NON-CONFORMANCE Region QLD1 Wednesday, 13 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE Region QLD1 Wednesday, 13 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TARONG#4
Duration: 13/12/2023 23:05 to 13/12/2023 23:10
Amount: -20 MW
Constraint: NC-Q_TARONG#4

Manager NEM Real Time Operations