Market Notices

114757MARKET INTERVENTION15/02/2024 01:28:07 PM

Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

Refer AEMO Electricity Participant Notice 114751

Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.

The instruction direction under National Electricity Law s116 to maintain demand above the required threshold is now expected to end at 1430 hrs 15/02/2024.


Manager NEM Real Time Operations
114753MARKET INTERVENTION15/02/2024 12:32:48 PM

Distributed PV Contingency 2 (DPVC2) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has taken action(s) to maintain power system security in South Australia at 1215 hrs 15/02/2024 due to a forecast Distributed PV Contingency (DPVC) condition.

AEMO actions may include the recall of planned outages, a direction and/or instruction to scheduled and non-scheduled generation, and/or an instruction direction to maintain DPV generation below a secure DPV generation threshold.

Manager NEM Real Time Operations
114751MARKET INTERVENTION15/02/2024 12:34:45 PM

Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.

The instruction direction under National Electricity Law s.116 to maintain demand above the required threshold is expected to end at 1330 hrs 15/02/2024.


Manager NEM Real Time Operations
114746MARKET INTERVENTION15/02/2024 11:14:28 AM

DPV Contingency 1 (DPVC1) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected there is an elevated risk of the contingent disconnection of Distributed PV (DPV) which, together with the risk of loss of scheduled generation, exceeds secure thresholds in the South Australia region from 1200 hrs 15/02/2024 to 1400 hrs 15/02/2024.

Maximum DPV generation forecast by the Australian Solar Energy Forecasting System 2 (ASEFS2) is 1735 MW at 1300 hrs and the secure ASEFS2 DPV generation limit for the forecast operating conditions is 1786 MW.

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in South Australia. This may result in action such as the recall of planned outages, direction of scheduled generation, curtailment of non-scheduled wind generation, and an instruction / direction to maintain DPV generation below a secure DPV generation threshold.

AEMO estimates the latest time at which it may need to intervene through an AEMO intervention event is 1130 hrs on 15/02/2024.

Manager NEM Real Time Operations
114744MARKET INTERVENTION15/02/2024 10:51:30 AM

Cancellation of Distributed PV Contingency 1 (DPVC1) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - DPVC1 - SA Region

Refer Market Notice 114743

The DPVC1 condition for 15/02/2024 is cancelled at 1045 hrs 15/02/2024.

Manager NEM Real Time Operations
114743MARKET INTERVENTION15/02/2024 09:21:02 AM

DPV Contingency 1 (DPVC1) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected there is an elevated risk of the contingent disconnection of Distributed PV (DPV) which, together with the risk of loss of scheduled generation, exceeds secure thresholds in the South Australia region from 1330 hrs 15/02/2024 to 1430 hrs 15/02/2024.

Maximum DPV generation forecast by the Australian Solar Energy Forecasting System 2 (ASEFS2) is 1716 MW at 1400 hrs and the secure ASEFS2 DPV generation limit for the forecast operating conditions is 1752 MW.

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in South Australia. This may result in action such as the recall of planned outages, direction of scheduled generation, curtailment of non-scheduled wind generation, and an instruction / direction to maintain DPV generation below a secure DPV generation threshold.

AEMO estimates the latest time at which it may need to intervene through an AEMO intervention event is 1230 hrs on 15/02/2024.

Manager NEM Real Time Operations
114741MARKET INTERVENTION15/02/2024 05:15:36 AM

Cancellation of Distributed PV Contingency 1 (DPVC1) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - DPVC1 - SA Region

Refer Market Notice 114740

The DPVC1 condition for 15/02/2024 is cancelled at 0510 hrs 15/02/2024.

Manager NEM Real Time Operations
114740MARKET INTERVENTION15/02/2024 01:41:43 AM

DPV Contingency 1 (DPVC1) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected there is an elevated risk of the contingent disconnection of Distributed PV (DPV) which, together with the risk of loss of scheduled generation, exceeds secure thresholds in the South Australia region from 1230 hrs 15/02/2024 to 1400 hrs 15/02/2024.
Maximum DPV generation forecast by the Australian Solar Energy Forecasting System 2 (ASEFS2) is 1737 MW at 1330 hrs and the secure ASEFS2 DPV generation limit for the forecast operating conditions is 1796 MW.

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in South Australia. This may result in action such as the recall of planned outages, direction of scheduled generation, curtailment of non-scheduled wind generation, and an instruction / direction to maintain DPV generation below a secure DPV generation threshold.
AEMO estimates the latest time at which it may need to intervene through an AEMO intervention event is 1130 hrs on 15/02/2024.

Manager NEM Real Time Operations
114724MARKET INTERVENTION14/02/2024 05:59:52 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 12/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 12/02/2024

Refer Market Notice 114536

The AEMO Intervention Event and all associated directions are cancelled from 1800 hrs 14/02/2024