113532RESERVE NOTICE20/01/2024 02:37:35 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1830 hrs 26/01/2024 to 1930 hrs 26/01/2024.
The forecast capacity reserve requirement is 1232 MW.
The minimum capacity reserve available is 1124 MW.


Manager NEM Real Time Operations
113531RESERVE NOTICE20/01/2024 02:31:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113477 has been updated at 1430 hrs 20/01/2024 to the following:

[1.] From 1830 hrs 25/01/2024 to 1930 hrs 25/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1111 MW.

Manager NEM RTO
113530RESERVE NOTICE20/01/2024 02:29:02 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113479 has been updated at 1430 hrs 20/01/2024 to the following:

[1.] From 1500 hrs 25/01/2024 to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 965 MW.

Manager NEM RTO
113527RESERVE NOTICE20/01/2024 01:25:55 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 21/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 21/01/2024 to 1900 hrs 21/01/2024.
The forecast capacity reserve requirement is 1249 MW.
The minimum capacity reserve available is 1082 MW.


Manager NEM Real Time Operations
113524NON-CONFORMANCE20/01/2024 12:15:21 PM

NON-CONFORMANCE Region SA1 Saturday, 20 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 20 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LKBONNY1
Duration: 20/01/2024 12:10 to 20/01/2024 12:15
Amount: 18 MW
Constraint: NC-S_LKBONNY1

Auto-generated on behalf of Manager NEM Real Time Operations
113479RESERVE NOTICE19/01/2024 03:29:01 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113410 has been updated at 1400 hrs 19/01/2024 to the following:

From 1900 hrs to 1930 hrs 25/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1258 MW.

AEMO Operations
113477RESERVE NOTICE19/01/2024 03:28:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1118 MW.

AEMO Operations
113476RESERVE NOTICE19/01/2024 03:27:03 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113409 is cancelled at 1400 hrs 19/01/2024.

AEMO Operations
113464NON-CONFORMANCE19/01/2024 07:05:14 AM

NON-CONFORMANCE Region NSW1 Friday, 19 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 19 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 19/01/2024 07:00 to 19/01/2024 07:05
Amount: 16 MW
Constraint: NC-N_MP2