Inter-Regional Transfer limit variation - Murraylink control unavailable - SA Region
Inter-Regional Transfer limit variation - Murraylink control unavailable - SA Region
AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.
Constraint Set I-CTRL_ISSUE_ML was invoked from 0550 hrs until further notice
This Constraint Set contains equations with the following interconnector on the LHS.
V-S-MNSP1
Manager NEM Real Time Operations
AEMO Intervention Event - Intervention price dispatch intervals - 25/04/2019
AEMO Intervention Event - Intervention price dispatch intervals - 25/04/2019
Refer AEMO Electricity Market Notice no. 68208
An AEMO Intervention Event occurred when AEMO issued a direction to maintain the power system in a secure operating state.
The AEMO Intervention Event commenced in the 0005 hrs dispatch interval and is forecast to apply until 0400 hrs 26/04/2019.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The direction is expected to affect dispatch quantities for intervention pricing purposes from the 0105 hrs dispatch interval on 25/04/2019.
Manager NEM Real Time Operations
Direction - South Australia region 25/04/2019
Direction - South Australia region 25/04/2019
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the South Australia region.
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided.
A further market notice will be issued when all directions related to this requirement have been cancelled.
For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region 25/04/2019.
Possible intervention to manage power system security in South Australia (SA) Region 25/04/2019.
The synchronous generating units expected to be synchronised in SA from 0400 hrs 25/04/2019 to 0400 hrs 26/04/2019 in Pre-dispatch published at 1600 hrs 24/04/2019 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 0000 hrs 25/04/2019, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Planned Software Change - MSATS B2B e-Hub SMP-121 & SMP-121.1
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: Planned Software Change - MSATS B2B e-Hub SMP-121 & SMP-121.1
Change Start Date & Time: 01/05/2019 17:30:00 AEST
Change End Date & Time: 01/05/2019 19:30:00 AEST
Outage Start Date & Time: 01/05/2019 17:30:00 AEST
Outage End Date & Time: 01/05/2019 17:30:00 AEST
Change Description:
This change addresses the following defects:
DFCT0021334 start/stop date time - invalid format in HubQueue report
DFCT0021865 AEMO not validating the input aseXMLs
Environment: Production
Participant Impact and Requirements:
Outage Expected during the release
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
MSATS (46.92 & 46.92.1) Planned Software Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS (46.92 & 46.92.1) Planned Software Release
Change Start Date & Time: 01/05/2019 17:30:00 AEST
Change End Date & Time: 01/05/2019 19:30:00 AEST
Outage Start Date & Time: 01/05/2019 17:30:00 AEST
Outage End Date & Time: 01/05/2019 19:30:00 AEST
Change Description:
The MSATS Production system will be upgraded with the MSATS 46.92 & 46.92.1 and includes the following functionality.
DFCT0019302 Meter register Identifier screen in MSATS to display Maintactflg value.
DFCT0020078 B2B NoticeofMeteringWorks validations in MSATS
DFCT0021280 additional fields for the Ombudsman Screen
DFCT0021657 allow for profile data source - edit screen to accept weights > 1
DFCT0021814 PersonNameType should be mandatory field
DFCT0021848 Life Support transactions in Translog search screen
DFCT0021866 MSATS v4.7 Requirements (changes effective from 20/05)
Environment: Production
Participant Impact and Requirements:
Awareness of this Outage. MSATS Production environment will be unavailable during the outage times mentioned above to perform the release activities.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region NSW1 Wednesday, 24 April 2019
NON-CONFORMANCE NSW1 Region Wednesday, 24 April 2019
AEMO declared a schedule generating unit non-conforming
Unit: VP6
Duration: 24/04/2019 06:45 to 24/04/2019 06:50
Amount: -34 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
RESERVE NOTICE MT PASA PUBLICATION 23 April 2019
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 68121 published on 16 April 2019.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
http://www.aemo.com.au/-/media/Files/Stakeholder_Consultation/Consultations/Electricity_Consultations/2016/EAAP/Reliability-Standard-Implementation-Guidelines.pdf
Forecasting
AEMO
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500 kV Line (Vic) - Voltage Control
Refer AEMO Electricity Market Notice 68152
The Hazelwood - South Morang No.1 500 kV Line has been returned to service.
The following constraint set was revoked at 0530 hrs 23/04/2019.
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations