[EventId:201901251020_review] Prices for interval 25-Jan-2019 10:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 25 January 2019
PRICES ARE SUBJECT TO REVIEW for dispatch interval 25-Jan-2019 10:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:201901251015_review] Prices for interval 25-Jan-2019 10:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1010 hrs on 25 January 2019
PRICES ARE SUBJECT TO REVIEW for dispatch interval 25-Jan-2019 10:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack of Reserve Level 3 (LOR3) in the Vic Region on 25/01/2019
The Forecast LOR3 condition in the Victoria region advised in AEMO Electricity Market Notice No. 66747 has been updated at 0940 hrs to the following:
From 1030 hrs to 1500 hrs 25/01/2019.
The maximum load (other than interruptible loads) forecast to be interrupted is 200 MW at [approximately] 1430 hrs.
AEMO is seeking a market response.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the Vic region - 25/01/2019
An Actual LOR2 condition has been declared for the Vic region from 0945 hrs.
The Actual LOR2 condition is forecast to exist until 1530 hrs.
The capacity reserve required is 560 MW
The minimum reserve available is 119 MW
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations
[EventId:201901250940_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 January 2019 09:40
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 25 January 2019
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 January 2019.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 0940 hrs on 25 January 2019.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
RERT DISPATCHED
PDPASA - Update of the Forecast Lack of Reserve Level 2 (LOR2) in the Vic Region on 25/01/2019
The Forecast LOR2 condition in the Vic region advised in AEMO Electricity Market Notice No. 66731 has been updated at 0840 hrs to the following:
1) From 0900 hrs 25/01/2019 to 1000 hrs 25/01/2019.
The forecast capacity reserve requirement is 560 MW.
The minimum capacity reserve available is 149 MW.
2) From 1500 hrs 25/01/2019 to 1600 hrs 25/01/2019.
The forecast capacity reserve requirement is 543 MW.
The minimum capacity reserve available is 265 MW.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 0900 hrs on 25/01/2019
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack of Reserve Level 3 (LOR3) in the Vic Region on 25/01/2019
From 1000 hrs to 1500 hrs 25/01/2019.
The maximum load (other than interruptible loads) forecast to be interrupted is 361 MW at [approximately] 1430 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 0900 hrs on 25/01/2019.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the VIC region - 25/01/2019
AEMO ELECTRICITY MARKET NOTICE
Actual Lack Of Reserve Level 1 (LOR1) in the VIC region - 25/01/2019
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 0800 hrs.
The Actual LOR1 condition is forecast to exist until 1630 hrs
The capacity reserve requirement is 1120 MW
The minimum capacity reserve available is 640 MW
Manager NEM Real Time Operations