Market Notices

112215GENERAL NOTICE12/12/2023 11:11:25 PM

Network Augmentation Commissioned - SA Region - 12/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 12/12/2023

Commissioned: Robertstown - Bundey No. 2 275 kV Line

Manager NEM Real Time Operations
112201RECALL GEN CAPACITY12/12/2023 10:59:40 AM

Request for Generator Recall Information for 14/12/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198. Additional generation in QLD could assist in alleviating the forecast LOR condition in NSW.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112200RECALL GEN CAPACITY12/12/2023 11:01:01 AM

Request for Generator Recall Information for 14/12/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 112198.

Please provide Generator Recall Information for the period 14/12/2023, by 1200 hrs on 13/12/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
112199NON-CONFORMANCE12/12/2023 09:25:17 AM

NON-CONFORMANCE Region SA1 Tuesday, 12 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 12 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: NBHWF1
Duration: 12/12/2023 09:00 to 12/12/2023 09:25
Amount: 17 MW
Constraint: NC-S_NBHWF1

Auto-generated on behalf of Manager NEM Real Time Operations
112173NON-CONFORMANCE11/12/2023 10:35:17 AM

NON-CONFORMANCE Region QLD1 Monday, 11 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 11 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5

Auto-generated on behalf of Manager NEM Real Time Operations
112172GENERAL NOTICE11/12/2023 11:08:03 AM

NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

VIC
Mildura Ap (39+ Deg C): 12th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
112162GENERAL NOTICE10/12/2023 09:05:21 PM

Network Augmentation Commissioned - SA Region - 10/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 10/12/2023

Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard

Manager NEM Real Time Operations
112140NON-CONFORMANCE09/12/2023 05:56:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
112120GENERAL NOTICE08/12/2023 05:35:38 PM

Network Augmentation Commissioned - NSW Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 08/12/2023

Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line

Manager NEM Real Time Operations