117065RECLASSIFY CONTINGENCY19/06/2024 07:24:55 AM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/06/2024 07:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117063

Auto-generated on behalf of Manager NEM Real Time Operations
     
117064RECLASSIFY CONTINGENCY19/06/2024 07:24:50 AM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 19/06/2024 07:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117062

Auto-generated on behalf of Manager NEM Real Time Operations
     
117063RECLASSIFY CONTINGENCY19/06/2024 06:20:35 AM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 19/06/2024 06:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
117062RECLASSIFY CONTINGENCY19/06/2024 06:20:36 AM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 19/06/2024 06:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
117061MARKET INTERVENTION18/06/2024 11:25:29 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
117043RECLASSIFY CONTINGENCY18/06/2024 10:20:15 AM

Update - Non-credible contingency event - VIC region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 18/06/2024

Refer AEMO Electricity Market Notice 117042

The cause of this non credible contingency event is not known at this stage..
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: VIC

Elements: Glenrowan No1 66kV Bus
Duration: 0903 hrs 18/06/2024 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
117042POWER SYSTEM EVENTS18/06/2024 10:16:34 AM

Non-credible contingency event - VIC region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 18/06/2024

At 0839 hrs the Glenrowan No1 66kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117014MARKET INTERVENTION14/06/2024 08:29:53 PM

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

Refer Market Notice 116996

AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.

Manager NEM Real Time Operations
     
117005PRICES UNCHANGED14/06/2024 02:46:56 PM

[EventId:202406141420_confirmed] Prices for interval 14-Jun-2024 14:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 14 June 2024

PRICES ARE NOW CONFIRMED for trading interval 14-Jun-2024 14:20.

In accordance with Market Notice 116992 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     