117314INTER-REGIONAL TRANSFER08/07/2024 08:28:55 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_559DA1A7 from 0825hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
117313INTER-REGIONAL TRANSFER08/07/2024 05:41:45 AM

Inter-regional transfer limit variation - 89 Lismore - Coffs 330kV Line - NSW region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - 89 Lismore - Coffs 330kV Line - NSW region - 08/07/2024

At 0511 hrs 08/07/2024 there was an unplanned outage of 89 Lismore - Coffs 330kV Line.

The following constraint set(s) invoked at 0525 hrs 08/07/2024
N-CHLS_89, N-DLETS_OS, N-X_MBTE_3

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117300INTER-REGIONAL TRANSFER06/07/2024 10:34:25 AM

Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Murraylink - SA region - 06/07/2024

A planned outage of Murraylink in the SA region was scheduled from 0700 hrs 28/06/2024 to 1700 hrs 09/07/2024.

The outage has been completed and Murraylink returned to service at 1035 hrs 06/07/2024

Constraint set(s) revoked: I-MURRAYLINK

Manager NEM Real Time Operations
     
117296MARKET SYSTEMS05/07/2024 03:30:41 PM

CHG0090731 | Production | MSATS and eMDM July Maintenance Release

Change Number: CHG0090731

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS and eMDM July Maintenance Release
Change Start Date & Time: 14/07/2024 10:00:00 AEST
Change End Date & Time: 14/07/2024 18:00:00 AEST
Outage Start Date & Time: 14/07/2024 10:00:00 AEST
Outage End Date & Time: 14/07/2024 18:00:00 AEST

Environment: Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

NOTE: The Outage is from 10:00 to 18:00 AEST which is 4 hours longer than the agreed maintenace window of 10:00 to 14:00 AEST.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
117290INTER-REGIONAL TRANSFER04/07/2024 02:18:46 PM

Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines - NSW region - 04/07/2024

A planned outage of Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines in the NSW region was scheduled from 0800 hrs 03/07/2024 to 1700 hrs 04/07/2024.

The outage has been completed and Crookwell- Gullen Range 3H and Bannaby - Crookwell 61 330 kV lines returned to service at 1405 hrs 04/07/2024

Constraint set(s) revoked: N-BYCR_61_15M and N-CRGR_3H

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.


Manager NEM Real Time Operations
     
117289INTER-REGIONAL TRANSFER04/07/2024 11:04:20 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 04/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore - Dunoon 9U7 132 kV line - NSW region - 04/07/2024

A planned outage of Lismore - Dunoon 9U7 132 kV line in the NSW region was scheduled from 0732 hrs 02/07/2024 to 1700 hrs 19/07/2024.

The outage has been completed and Lismore - Dunoon 9U7 132 kV line returned to service at 1105 hrs 04/07/2024

Constraint set(s) revoked: N-LSDU_9U6

This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Manager NEM Real Time Operations
     
117285SETTLEMENTS RESIDUE03/07/2024 05:55:22 PM

[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Refer to market notice: 117283

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.

This is an AEMO autogenerated Market Notice.
     
117283SETTLEMENTS RESIDUE03/07/2024 05:30:25 PM

[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117258MARKET SYSTEMS01/07/2024 10:32:38 AM

CHG0090790 | Completed | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Change Number: CHG0090790

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Gas FRC - CATS

Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm