Market Notices

117375INTER-REGIONAL TRANSFER19/07/2024 07:03:12 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117372

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1835 hrs.

Manager NEM Real Time Operations
     
117374INTER-REGIONAL TRANSFER19/07/2024 06:01:53 PM

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions - 19/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood interconnector - SA and Vic regions- 19/07/2024

Refer to reclassification Market notice 117373

The following constraint set(s) invoked at 1740 hrs 19/07/2024
I-SV_250 , I-VS_250

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Manager NEM Real Time Operations
     
117372INTER-REGIONAL TRANSFER19/07/2024 04:41:55 PM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 1640 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
     
117371INTER-REGIONAL TRANSFER19/07/2024 04:20:09 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 117368

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1620 hrs.

Manager NEM Real Time Operations
     
117368INTER-REGIONAL TRANSFER19/07/2024 03:24:41 PM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 1530 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
     
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
     
117355INTER-REGIONAL TRANSFER16/07/2024 04:09:23 PM

Inter-regional transfer limit variation -Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tungkillo-Tailem_Bnd 1 275kV LINE - SA region - 16/07/2024

A planned outage of Tungkillo-Tailem_Bnd 1 275kV LINE in the SA region was scheduled from 0845 hrs 16/07/2024 to 1630 hrs 16/07/2024.

The outage has been completed and Tungkillo-Tailem_Bnd 1 275kV LINE returned to service at 1255 hrs 16/07/2024

Constraint set(s) revoked: S-TBTU

Manager NEM Real Time Operations
     
117343NON-CONFORMANCE14/07/2024 04:50:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 14/07/2024 16:35 to 14/07/2024 16:50
Amount: -66 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117342NON-CONFORMANCE14/07/2024 01:45:18 AM

NON-CONFORMANCE Region VIC1 Sunday, 14 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 14 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS1
Duration: 14/07/2024 01:40 to 14/07/2024 01:45
Amount: -35 MW
Constraint: NC-V_YWPS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X