Market Notices

116577MARKET INTERVENTION10/05/2024 04:56:42 PM

Direction - SA region 10/05/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 10/05/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 10/05/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116574MARKET INTERVENTION10/05/2024 02:17:13 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116573

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 11/05/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 10/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116573MARKET INTERVENTION10/05/2024 12:16:25 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 11/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116571NON-CONFORMANCE10/05/2024 10:05:15 AM

NON-CONFORMANCE Region QLD1 Friday, 10 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 10 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OAKEY2SF
Duration: 10/05/2024 08:35 to 10/05/2024 10:05
Amount: 35 MW
Constraint: NC-Q_OAKEY2SF

Auto-generated on behalf of Manager NEM Real Time Operations
     
116565RESERVE NOTICE09/05/2024 04:16:23 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116559 has been updated at 1615 hrs to the following:

[1.] From 1630 hrs 09/05/2024 to 1900 hrs 09/05/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 979 MW.

Manager NEM Real Time Operations
     
116562MARKET INTERVENTION09/05/2024 02:03:44 PM

Cancellation - Possible intervention to manage power system security in SA region 10/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region 10/05/2024

Refer Market Notice 116561

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1400 hrs 09/05/2024.

Manager NEM Real Time Operations
     
116561MARKET INTERVENTION09/05/2024 12:45:39 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 10/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116559RESERVE NOTICE09/05/2024 09:42:35 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 09/05/2024 to 1830 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1236 MW.

Manager NEM Real Time Operations
     
116558RESERVE NOTICE09/05/2024 08:41:33 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116556 is cancelled at 0840 hrs 09/05/2024.

Manager NEM Real Time Operations
     