Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 02/06/2016
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 02/06/2016
The Forecast LOR1 condition in the Tasmania Region advised in AEMO Electricity Market Notice No. 53580 is cancelled at 0710hrs 02/06/2016.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PD PASA - 02/06/2016
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PD PASA - 02/06/2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0730 hrs to 0830 hrs Thursday, 2 June 2016
The contingency capacity reserve required is 288 MW
The minimum reserve available is 264 MW
Manager NEM Real Time Operations
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 01/06/2016
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 01/06/2016
The Forecast LOR1 condition in the Tasmania Region advised in AEMO Electricity Market Notices No. 53574 and 53575 is cancelled at 0741hrs 01/06/2016.
Manager NEM Real Time Operations
Update - Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
Update to Market Notice 53574
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0700 hrs to 0930 hrs 01/06/16
The contingency capacity reserve required is 263 MW
The minimum reserve available is 190 MW
Manager NEM Real Time Operations
orecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0730 hrs to 0830 hrs 01/06/16
The contingency capacity reserve required is 263MW
The minimum reserve available is 254 MW
Manager NEM Real Time Operations
Cancellation of the Forecast (LOR1) condition in the NSW region - PDPASA - 30 May 2016
Cancellation of the Forecast (LOR1) condition in the NSW region - PDPASA - 30 May 2016
The Forecast LOR1 condition in the NSW Region advised in AEMO Electricity Market Notice No. 53559 is cancelled at 1345 hrs 29 May 2016.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region - PDPASA - 30 May 2016
Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region - PDPASA - 30 May 2016
AEMO declares a Forecast LOR1 condition for the NSW Region.
From 1800 hrs to 1900 hrs 30 May 2016
The contingency capacity reserve required is 1400 MW
The minimum reserve available is 1264 MW
Manager NEM Real Time Operations