Market Notices

98621RESERVE NOTICE20/06/2022 01:20:56 PM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 21/06/2022 to 1930 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 426 MW at 1730 hrs.

[2.] From 2000 hrs 21/06/2022 to 2200 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 405 MW at 2100 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 21/06/2022

AEMO Operations
98617RESERVE NOTICE20/06/2022 01:06:01 PM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the Vic Region beginning on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the Vic region for the following period:

[1.] From 1730 hrs 21/06/2022 to 2230 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1586 MW at 2030 hrs.

[2.] From 2330 hrs 21/06/2022 to 0000 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 178 MW at 2330 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 21/06/2022.

AEMO Operations
98616RESERVE NOTICE20/06/2022 01:04:42 PM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region beginning on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1730 hrs 21/06/2022 to 2230 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1444 MW at 1830 hrs.

[2.] From 2330 hrs 21/06/2022 to 0000 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 178 MW at 2330 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 21/06/2022.

AEMO Operations
98615RESERVE NOTICE20/06/2022 12:55:45 PM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98603 has been updated at 1200 hrs 20/06/2022 to the following:

From 1830 hrs to 2030 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 378 MW at 2000 hrs.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
98605RESERVE NOTICE20/06/2022 11:52:21 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 20/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98598 is cancelled at 1130 hrs 20/06/2022

AEMO Operations
98604RESERVE NOTICE20/06/2022 11:16:07 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition on 22/06/2022 in the SA region advised in AEMO Electricity Market Notice No. 98508 is cancelled at 1000 hrs 20/06/2022.

AEMO Operations
98603RESERVE NOTICE20/06/2022 11:14:20 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

From 1930 hrs to 2030 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 257 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
98601RESERVE NOTICE20/06/2022 11:08:23 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 21/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:

From 2000 hrs to 2030 hrs 21/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 267 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
98598RESERVE NOTICE20/06/2022 10:59:27 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 20/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98594 has been updated at 1030 hrs to the following:

[1.] From 2000 hrs 20/06/2022 to 2030 hrs 20/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 209 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1930 hrs on 20/06/2022.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.