NON-CONFORMANCE Region VIC1 -26 May 2016
NON-CONFORMANCE VIC1 Region - 26 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BDL02
Duration: 26/05/2016 23:05 to 26/05/2016 23:10
Amount: -35 MW
Constraint: NC-V_BDL02
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 26 May 2016
NON-CONFORMANCE QLD1 Region Thursday, 26 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR3
Duration: 26/05/2016 08:20 to 26/05/2016 08:30
Amount: -36 MW
Constraint: NC-Q_BRAEMAR3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 25 May 2016
NON-CONFORMANCE VIC1 Region Wednesday, 25 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 25/05/2016 00:00 to 25/05/2016 00:25
Amount: -27 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 and 30 May 2016
Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 May and 30 May 2016.
There are planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line between 0630-1630hrs on 25 May 2016 and 0630-1800hrs on 30 May 2016.
During these outages, South Australia region remains connected to the NEM for the first contingency (trip of the Moorabool - Sydenham No.2 500 kV line). However, there is a potential risk of South Australia region separation from the rest of the NEM for the subsequent contingency following the first contingency.
AEMO will invoke the following FCAS regulation constraint sets after the first contingency during this outage to secure the power system in South Australia region.
F-S_LREG_0035
F-S_RREG_0035
Refer to AEMO Network Outage Schedule (NOS) for further details
Operations Planning
NON-CONFORMANCE Region NSW1 Monday, 23 May 2016
NON-CONFORMANCE NSW1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: SITHE01
Duration: 23/05/2016 06:35 to 23/05/2016 08:30
Amount: 23 MW
Constraint: NC-N_SITHE01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 23 May 2016
NON-CONFORMANCE SA1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: WATERLWF
Duration: 23/05/2016 03:35 to 23/05/2016 05:10
Amount: 107 MW
Constraint: NC-S_WATERLWF
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 23 May 2016
NON-CONFORMANCE VIC1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: HWPS3
Duration: 23/05/2016 04:20 to 23/05/2016 04:30
Amount: 11 MW
Constraint: NC-V_HWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 22 May 2016
NON-CONFORMANCE VIC1 Region Sunday, 22 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 22/05/2016 08:35 to 22/05/2016 08:40
Amount: 20 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 20 May 2016
NON-CONFORMANCE VIC1 Region Friday, 20 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS1
Duration: 20/05/2016 09:35 to 20/05/2016 10:05
Amount: 19 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations