Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Saturday, 4 June 2016
NON-CONFORMANCE VIC1 Region Saturday, 4 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: BDL02
Duration: 04/06/2016 14:30 to 04/06/2016 14:40
Amount: 20 MW
Constraint: NC-V_BDL02
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 4 June 2016
NON-CONFORMANCE VIC1 Region Saturday, 4 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: BDL01
Duration: 04/06/2016 14:30 to 04/06/2016 14:35
Amount: 20 MW
Constraint: NC-V_BDL01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 3 June 2016
NON-CONFORMANCE QLD1 Region Friday, 3 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR2
Duration: 03/06/2016 05:35 to 03/06/2016 05:40
Amount: -150 MW
Constraint: NC-Q_BRAEMAR2
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 02/06/2016
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 02/06/2016
The Forecast LOR1 condition in the Tasmania Region advised in AEMO Electricity Market Notice No. 53580 is cancelled at 0710hrs 02/06/2016.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PD PASA - 02/06/2016
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PD PASA - 02/06/2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0730 hrs to 0830 hrs Thursday, 2 June 2016
The contingency capacity reserve required is 288 MW
The minimum reserve available is 264 MW
Manager NEM Real Time Operations
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 01/06/2016
Cancellation of the Forecast (LOR1) condition in the Tasmania region - PDPASA - 01/06/2016
The Forecast LOR1 condition in the Tasmania Region advised in AEMO Electricity Market Notices No. 53574 and 53575 is cancelled at 0741hrs 01/06/2016.
Manager NEM Real Time Operations
Update - Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
Update to Market Notice 53574
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0700 hrs to 0930 hrs 01/06/16
The contingency capacity reserve required is 263 MW
The minimum reserve available is 190 MW
Manager NEM Real Time Operations
orecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
Forecast Lack Of Reserve Level 1 (LOR1) in the Tasmania Region - PDPASA - 1 June 2016
AEMO declares a Forecast LOR1 condition for the Tasmania Region.
From 0730 hrs to 0830 hrs 01/06/16
The contingency capacity reserve required is 263MW
The minimum reserve available is 254 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016
NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR3
Duration: 31/05/2016 17:45 to 31/05/2016 17:55
Amount: 9 MW
Constraint: NC-Q_BRAEMAR3
Auto-generated on behalf of Manager NEM Real Time Operations