53249INTER-REGIONAL TRANSFER15/05/2016 02:45:03 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control - Sunday, 15th May 2016

The Hazelwood - South Morang No.1 500kV Line has been de-energised to manage voltages in the VIC region.

The following constraint set was invoked at 0230 hrs

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

NSW1-QLD1
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Schedule for further details and return to service times

Manager NEM Real Time Operations
53248INTER-REGIONAL TRANSFER15/05/2016 01:10:35 AM

Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Sunday, 15 May 2016

The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.

The following constraint set was invoked at 0110 hrs until further notice.

Q-MRGB_8848_8849

The constraint set contains equations with the following interconnectors on the LHS.

NSW-QLD1
N-Q-MNSP1



Manager NEM Real Time Operations
53237NON-CONFORMANCE14/05/2016 11:09:12 PM

NON-CONFORMANCE Region VIC1 Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 14 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: YWPS1
Duration: 14/05/2016 22:50 to 14/05/2016 22:55
Amount: -57 MW
Constraint: NC-V_YWPS1

Manager NEM Real Time Operations
53216INTER-REGIONAL TRANSFER14/05/2016 09:23:21 AM

Cancellation - Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

Refer to MN 53189

The Greenbank to Middle Ridge (8848) 275kV Line was returned to service.

The following constraint set was revoked at 0650 hrs until further notice.

Q-MRGB_8848_8849

The constraint set contains equations with the following interconnectors on the LHS.

NSW-QLD1
N-Q-MNSP1

Refer to AEMO Network Outage Schedule for further details.

Manager NEM Real Time Operations
53209NON-CONFORMANCE14/05/2016 08:10:11 AM

NON-CONFORMANCE Region TAS1 Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE TAS1 Region Saturday, 14 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: TREVALLN
Duration: 14/05/2016 07:50 to 14/05/2016 08:10
Amount: -12 MW
Constraint: NC-T_TREVALLN

Auto-generated on behalf of Manager NEM Real Time Operations
53194INTER-REGIONAL TRANSFER14/05/2016 05:53:06 AM

Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

Refer MN 53191

The Tarong to South Pine (832) 275kV Line has been returned to service.

The following constraint set was revoked at 0550 hrs..

Q-TRSP_832

The constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1


Manager NEM Real Time Operations
53191INTER-REGIONAL TRANSFER14/05/2016 02:03:43 AM

Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

Refer MN 53190

The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.

The following constraint set was invoked at 0200 hrs until further notice.

Q-TRSP_832

The constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1


Manager NEM Real Time Operations


53190INTER-REGIONAL TRANSFER14/05/2016 02:00:13 AM

Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Friday, 13 May 2016

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Friday, 13 May 2016

The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.

The following constraint set was invoked at 0200 hrs until further notice.

Q-TRSP_832

The constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1


Manager NEM Real Time Operations

53189INTER-REGIONAL TRANSFER14/05/2016 01:07:26 AM

Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016

The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.

The following constraint set was invoked at 0105 hrs until further notice.

Q-MRGB_8848_8849

The constraint set contains equations with the following interconnectors on the LHS.

NSW-QLD1
N-Q-MNSP1

Refer to AEMO Network Outage Schedule for further details.

Manager NEM Real Time Operations