116579RECLASSIFY CONTINGENCY10/05/2024 05:54:50 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 10/05/2024 17:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 116578

Auto-generated on behalf of Manager NEM Real Time Operations
     
116578RECLASSIFY CONTINGENCY10/05/2024 04:51:05 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 10/05/2024 16:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
116572RECLASSIFY CONTINGENCY10/05/2024 10:13:53 AM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions.

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in the NEM regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
     
116571NON-CONFORMANCE10/05/2024 10:05:15 AM

NON-CONFORMANCE Region QLD1 Friday, 10 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 10 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: OAKEY2SF
Duration: 10/05/2024 08:35 to 10/05/2024 10:05
Amount: 35 MW
Constraint: NC-Q_OAKEY2SF

Auto-generated on behalf of Manager NEM Real Time Operations
     
116568RECLASSIFY CONTINGENCY10/05/2024 06:01:54 PM

Cancellation - Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned outage : Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer - Qld region.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation - Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned outage.

AEMO considers the occurrence of a non-credible contingency event due to planned outage advised in AEMO Electricity Market Notice 116557 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Region: Qld

Elements: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer

Cancellation time: 1800 hrs 10/05/2024

Constraint set(s) invoked:
Nil

Manager NEM Real Time Operations
     
116557RECLASSIFY CONTINGENCY09/05/2024 01:58:22 PM

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer - Qld region.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event. AEMO considers the simultaneous trip of the following elements to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: Qld

Elements: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer

Duration: 1400 hrs 09/05/2024 until further notice

Constraint set(s) invoked:
Nil

Manager NEM Real Time Operations
     
116543INTER-REGIONAL TRANSFER08/05/2024 03:50:23 PM

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.

The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116525INTER-REGIONAL TRANSFER08/05/2024 12:11:09 PM

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.

The outage has been cancelled at 1154 hrs 08/05/2024

Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1

Manager NEM Real Time Operations
     
116518RECLASSIFY CONTINGENCY08/05/2024 01:09:54 AM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 08/05/2024 01:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 116517

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm