NON-CONFORMANCE Region QLD1 Wednesday, 29 November 2023
NON-CONFORMANCE QLD1 Region Wednesday, 29 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 29/11/2023 09:15 to 29/11/2023 09:30
Amount: -13 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 28 November 2023
NON-CONFORMANCE QLD1 Region Tuesday, 28 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-1
Duration: 28/11/2023 12:00 to 28/11/2023 12:25
Amount: -16 MW
Constraint: NC-Q_STAN-1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 27 November 2023
NON-CONFORMANCE QLD1 Region Monday, 27 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE3
Duration: 27/11/2023 23:15 to 27/11/2023 23:20
Amount: 25 MW
Constraint: NC-Q_GSTONE3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 27 November 2023
NON-CONFORMANCE QLD1 Region Monday, 27 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 27/11/2023 17:15 to 27/11/2023 17:25
Amount: -21 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 27 November 2023
NON-CONFORMANCE QLD1 Region Monday, 27 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-2
Duration: 27/11/2023 09:00 to 27/11/2023 09:05
Amount: -57 MW
Constraint: NC-Q_STAN-2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 24 November 2023
NON-CONFORMANCE NSW1 Region Friday, 24 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 24/11/2023 17:00 to 24/11/2023 17:15
Amount: -13 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 16 November 2023
NON-CONFORMANCE SA1 Region Thursday, 16 November 2023
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TIBG1, TIBL1
Aggregate Dispatch Group: TIBESS_ADG1
Duration: 16/11/2023 23:05 to 16/11/2023 23:25
Amount: -26 MW
Constraint: NC-S_TIBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 16 November 2023
NON-CONFORMANCE QLD1 Region Thursday, 16 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#1
Duration: 16/11/2023 21:20 to 16/11/2023 21:45
Amount: -14 MW
Constraint: NC-Q_TARONG#1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 16 November 2023
NON-CONFORMANCE QLD1 Region Thursday, 16 November 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YABULU2
Duration: 16/11/2023 15:45 to 16/11/2023 15:55
Amount: 26 MW
Constraint: NC-Q_YABULU2
Auto-generated on behalf of Manager NEM Real Time Operations