[EventId:201609282035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 28 September 2016 20:35
Issued by Australian Energy Market Operator Ltd at 2035 hrs on 28 September 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 28 September 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2035 hrs on 28 September 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201609222000_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 September 2016 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 22 September 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 September 2016.
Refer to market notice: 54947
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2000 hrs on 22 September 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201609221840_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 September 2016 18:40
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 22 September 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 September 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1840 hrs on 22 September 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607131130_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 13 July 2016 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 13 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Refer to market notice: 54468
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1130 hrs on 13 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607131030_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 13 July 2016 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1030 hrs on 13 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607131000_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 13 July 2016 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Refer to market notice: 54466
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1000 hrs on 13 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607130900_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 13 July 2016 09:00
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 13 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 0900 hrs on 13 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607121900_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 12 July 2016 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 12 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Refer to market notice: 54455
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1900 hrs on 12 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607121800_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 12 July 2016 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 12 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1800 hrs on 12 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.