91697RESERVE NOTICE14/10/2021 03:13:58 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/10/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 91688 has been updated at 1500 hrs to the following:

[1.] From 1730 hrs 14/10/2021 to 1900 hrs 14/10/2021.
The forecast capacity reserve requirement is 1113 MW.
The minimum capacity reserve available is 1010 MW.

[2.] From 1930 hrs 14/10/2021 to 2000 hrs 14/10/2021.
The forecast capacity reserve requirement is 1103 MW.
The minimum capacity reserve available is 971 MW.


Manager NEM Real Time Operations
91695RECLASSIFY CONTINGENCY14/10/2021 02:12:00 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 & No.3 220 kV Lines line and Numurkah Solar Farm line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 & No.3 220 kV Lines and Numurkah Solar Farm

Duration: 14/10/2021 14:11 until further notice

Constraint set(s) invoked:
V-NIL_DDGN_NSF_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
91694RECLASSIFY CONTINGENCY14/10/2021 02:10:20 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 14/10/2021 14:10 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
91693GENERAL NOTICE14/10/2021 01:57:49 PM

Daily planned outage of Heywood No.1 500 kV busbar in the Victoria region on 25, 26, 27, 28 and 29 October 2021

AEMO ELECTRICITY MARKET NOTICE

The Heywood No.1 500 kV busbar in the Victoria (VIC) region is planned to be out of service from:
- 0400 hrs to 1000 hrs on 25/10/2021;
- 0400 hrs to 1000 hrs on 26/10/2021;
- 0300 hrs to 1000 hrs on 27/10/2021;
- 0300 hrs to 1000 hrs on 28/10/2021; and
- 1400 hrs to 1600 hrs on 29/10/2021.

A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM. If separation occurs, load may be interrupted due to the operation of the Automatic Under Frequency Load Shedding (AUFLS) scheme in SA.

The credible separation contingency is managed as follows:

- When power transfer is from SA to VIC, contingency lower FCAS will be sourced from SA.
- When power transfer is from VIC to SA, due to the 47-52Hz island separation frequency band advised by the SA jurisdiction, contingency raise FCAS is not sourced in SA and the AUFLS scheme may respond to low frequency events.
- Power transfer will be restricted on VIC - SA interconnector (Heywood interconnector) to manage system security following the loss of the next contingency.

Forecast capacity reserves in the SA region are currently sufficient to meet electricity demand during the planned outage.

The following constraint sets have been invoked for this outage:

F-I-HYSE
S-X_BC_CP
V-HYTX_M12
V-HY_500BUS
I-VS_050

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
91690RECLASSIFY CONTINGENCY14/10/2021 11:34:10 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 14/10/2021 11:34 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
91688RESERVE NOTICE14/10/2021 10:19:58 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/10/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 14/10/2021 to 2000 hrs 14/10/2021.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 769 MW.


Manager NEM Real Time Operations
91687RECLASSIFY CONTINGENCY14/10/2021 09:34:40 AM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 14/10/2021 09:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 91686

Auto-generated on behalf of Manager NEM Real Time Operations
91686RECLASSIFY CONTINGENCY14/10/2021 08:29:30 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 14/10/2021 08:29 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
91685MARKET SYSTEMS14/10/2021 08:16:28 AM

CHG0070443 | Completed | Production | MSATS - Customer Switching Retail deployment to the AEMO Production environment.

Change Number: CHG0070443
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - Customer Switching Retail deployment to the AEMO Production environment.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm