Indicative change program
This table includes the workstream and change process with indicative timeframes for documents that have been identified to change for the IESS project. Please select the document link to be taken to the consultation page where the current status of the change process can be found.
For all queries, please contact IESS@aemo.com.au.
Workstream |
Change Process Type |
Change Documents |
Process Commencement |
First round Submissions due |
Second round commencement |
Second round Submissions due |
Final Published |
---|---|---|---|---|---|---|---|
Settlements & Prudentials |
Standard |
25 Sep-23 |
20 Oct-23 |
17 Nov-23 |
15 Dec-23 |
TBC |
|
Settlements & Prudentials |
Standard |
14 Aug-23 |
22 Sep-23 |
10 Nov-23 |
27 Nov-23 |
15 Dec-23 |
|
National Connections |
Minor or administrative |
Guideline and Template for Preparation of a Releasable User Guide (RUG) |
Early February 2024 |
||||
National Connections |
Minor or administrative |
System Strength Impact Assessment Guideline |
Q1 2024 |
||||
Operations & Dispatch |
Minor or administrative |
SO_OP_3705 Dispatch Procedure Regulation FCAS Contribution Factors Procedure Demand terms in EMMS Data Model |
Nov/Dec |
|
|
|
|
Electricity Market Monitoring |
Minor or administrative |
Intervention Pricing Methodology
Spot Market Operations Timetable
Market Suspension Compensation Methodology
SO_OP_3707: Procedures for issue of directions and clause 4.8.9 instructions |
4 Sep-23 |
29 Sep-23 |
|
|
3 June 2024 |
Operations & Dispatch |
Minor or administrative |
Forward Looking Loss Factor Calculation Methodology |
4 Sep-23 |
29 Sep-23 |
|
|
3 June 2024 |
National Connections |
Minor or administrative |
Generation alterations in the NEM except Victoria process map Clarification of Generator Technical Performance Requirements (S5.2.5) Generator Connection Application Checklist Generator Connection R1 Submission Checklist |
Q1 2024 |
|
|
|
|
Settlements |
Minor or administrative |
Methodology for the allocation and distribution of settlements residue NEM Settlements Revision Policy Settlements guide to ancillary service payments and recovery NEM Direction Compensation Recovery NMAS Recovery Reconciliation File – Overview NEM Daily Energy Summary UFE Fact Sheet AEMO Statement Layouts Wholesale Demand Response Guidelines |
Q1 2024 |
|
|
|
|
Forecasting & Planning |
Minor or administrative |
Demand Side Participation Information Guidelines
|
1 Sep-23 |
29 Sep-23 |
31 Oct 2023 |
28 Nov 2023 |
20 Dec 2023 |
Forecasting & Planning |
Minor or administrative |
Connection point forecasting methodology Electricity demand forecasting methodology information paper |
May 2024 |
|
|
|
|
Electricity Market Monitoring |
Minor or administrative |
SO_OP_3705 Dispatch Procedure |
Q1 2024 |
||||
Operations & Dispatch |
Minor or administrative |
Regulation FCAS Contribution Factors Procedure |
Q1 2024 |
||||
Retail & Metering - Metering |
Standard
|
6 Mar-23 |
3 Apr-23 |
12 Jun-23 |
10 Jul-23 |
18 Sep-23 |
|
Retail & Metering – B2B
|
Minor and administrative |
B2B Hub accreditation document |
Q2 2024 |
|
|
|
|
Operations & Dispatch |
Minor or administrative |
21 Jul-22 |
12 Aug-22 |
n/a |
n/a |
14 Sep-22 |
|
Operations & Dispatch |
Minor or administrative |
28 Nov-22 |
20 Jan-23 |
n/a |
n/a |
10 Feb-23 |
|
Operations & Dispatch |
Minor or administrative |
Regulation FCAS Contribution Factors Procedure (Causer Pays) |
15 Aug-22 |
26 Aug-22 |
n/a |
n/a |
14 Sep-22 |
Forecasting & Planning |
Minor or administrative |
ASEFS Energy Conversion Model and
|
22 Aug-22 |
2 Sep-22 |
n/a |
n/a |
19 Sep-22 |
Operations & Dispatch |
Minor or administrative |
2 Dec-22 |
10 Feb-23 |
14 Apr-23 |
19 May-23 |
14 Jul-23 |
|
Operations & Dispatch |
Minor or administrative |
5 Sep-22 |
16 Sep -22 |
n/a |
n/a |
3 Oct -22 |
|
Settlements & Prudentials |
Standard Consultation
Review under NER 3.13.14 (a), (e) |
Carbon Dioxide Equivalent Intensity Index Procedures |
No consultation to be undertaken |
|
|
|
|
Settlements & Prudentials |
Minor or administrative |
7 Nov-22 |
18 Nov-22 |
|
|
12 Dec-22 |
|
Connections & Registrations |
Minor or administrative |
System strength impact assessment guidelines |
26 Apr-22 |
1 Jun-22 |
29 Jul-22 |
19 Aug-22 |
6 Jun-23 |
Connections & Registrations |
Standard |
Guide to Generator Exemptions and Classifications of Generating Units |
2 Nov-22 |
21 Dec-22 |
14 Feb-23 |
14 Mar-23 |
1 June-23 |
Operations & Dispatch |
|
|
No IESS changes |
|
|
|
|
Forecasting & Planning |
Standard |
Energy Adequacy Assessment Projection guidelines ESOO & Reliability forecasting methodology Spot Market Operations Timetable |
31 Oct-22 |
28 Nov-22 |
3 Feb-23 |
3 Mar-23 |
24 Apr-23 |
Operations & Dispatch |
Minor or administrative |
21 Nov-22 |
20 Dec-22 |
n/a |
n/a |
22 Jun-23 |
|
National Connections |
Minor or Administrative |
28 Feb-23 |
7 Mar-23 |
n/a |
n/a |
15 Mar-23 |